作文一:《土木工程毕业设计》19200字
毕 业 论 文
题 目 : 施工组织设计
学 院 :
年级、 专业 :
学 生 姓 名 :
学 号 :
指 导 教 师 :
完 成 时 间 :
目 录
第一章 绪 论 ......................................................................................... 6 1.1 施工组织设计的概念 ........................................................................ 6 1.2 施工组织设计的作用 ........................................................................ 6 1.3 施工组织设计的内容及分类 ............................................................ 8 1.4 施工组织设计的编制 ........................................................................ 9 1.5 进度计划的概念及作用 .................................................................. 10 1.6 施工进度计划的编制 ...................................................................... 10 第二章 射洪县新建法院审判楼工程的施工组织设计研究与分析 ........ 12 2.1 工程概况及工程特点 ...................................................................... 12 2.2 人员配备计划 ................................................................................... 16 2.3 工程的总体部署介绍及分析 .......................................................... 16 2.4 工程进度计划分析 .......................................................................... 22 第三章 射洪县法院审判综合楼程进度研究及对策 ................................ 26 3.1 施工总进度延误原因分析及解决方案 .......................................... 26 3.2 工程月进度及施工工期拖延原因分析及解决方案 ...................... 29 结 论 . .............................................................................................................. 34
摘 要
现代化的建筑工程施工是一项多工种、多专业的复杂的系统工程。在 一个建筑工地上进行建筑生产,要有各种建筑材料、施工机具和一定生产 经验及劳动技能的劳动者;要遵照建筑生产规律,遵守生产的技术规范以 及技术文件的规定。 如何将劳动者、 材料、 机具在空间上按照一定的位置, 时间上按照一定的顺序,数量上按照一定的比例有机的组织起来,实行统 一的指挥,以期达到预期的目标,是建筑施工组织和管理的核心问题。建 筑施工组织对统筹建筑施工全过程、促进技术进步、实现安全文明施工、 增强企业竞争能力、促进建筑业的发展起到关键作用。
施工组织设计就是对工程建设项目整个施工过程的构思设想和具体 安排 , 是施工组织管理工作的核心和灵魂。其目的是使工程速度快、质量 好、效益高 , 使整个工程在施工中获得相对的最优效果。工程施工是一项 十分复杂的组织管理工作 , 而土木产品与一般工业产品相比 , 有以下一些 显著的特点。产品地点的固定性:产品生根于大地 , 根据使用要求被分散 固定于不同的地点,一旦定位,就将永久固定。生产工人、机械设备的流 动性:由于产品地点的固定性,所以生产工人、机械设备等都要随施工地 点的不断变动而不断进行流动。
施工组织设计是指导一个拟建或在建工程进行施工准备或施工生产 的技术经济文件。 施工组织设计的编制依据是根据国家对建设项目的相关 要求以及主、客观条件,对工程施工生产的全过程采用科学的方法所进行 的一系列筹划安排活动,针对活动过程可预控活动结果 [1]。
ABSTRACT
Modern building engineering construction is a multi-disciplinary, multi professional plex system engineering. For the construction of production at a construction site, workers have all kinds of building materials, construction machinery and production experience and work skills; must obey the laws of building production, ply with the technical specifications for production and technical documents. How will the labor, materials, machines and tools in the space according to a certain position, time according to the order of, the number according to certain proportion organic organization, unified mand, in order to achieve the desired goal, is the core of construction organization and management issues. The construction organization to coordinate the whole construction process, promote technological progress, to achieve safe and civilized construction, is the key to enhance the development of the enterprise petition ability, promote the construction of the play.
Construction organization design is the construction of the project throughout the construction process of the idea of ideas and specific arrangements, is the core and soul of the construction organization and management. Its purpose is to make the project speed, good quality, high efficiency, so that the whole project to
obtain the relative effect of the optimal in construction. Engineering construction is a very plex organization and management, and civil products pared with the general industrial products, there are some notable characteristics. Fixed product place: product rooted in the earth, according to the use requirements are fixed in different locations, once in position, it will be permanently fixed. Flow of production workers, machinery and equipment: because of the fixed location of the product, so the production workers, machinery and equipment will change with the construction site and continuous flow.
Construction organization design is guided by a proposed or under construction project construction preparation and construction technology economy file. Based on the preparation of the construction organization design is in accordance with the relevant requirements of the state on construction project as well as the subjective and objective conditions, the construction of the entire process of production using scientific methods for a series of planning activities, the activities of controllable activity results 。
第一章 绪 论
1.1 施工组织设计的概念
一个建设项目的施工,可以有不同的施工顺序;每一个施工过程可以 采用不同的施工方案;每一种构件可以采用不同的生产方式;每一种运输 工作可以采用不同的方式和工具;现场施工机械、各种堆物、临时设施和 水电线路等可以有不同的布置方案; 开工前的一系列施工准备工作可以用 不同的方法进行。不同的施工方案,其效果是不一样的。施工组织设计是 指针对拟建的工程项目,在开工前针对工程本身特点和工地具体情况,按 照工程的要求,对所需的施工劳动力、施工材料、施工机具和施工临时设 施,经过科学计算、精心对比及合理的安排后编制出的一套在时间和空间 上进行合理施工的战略部署文件 [1~3]。通常由一份施工组织设计说明书、 一张工程计划进度表、一套施工现场平面布置图组成。施工组织设计是工 程施工的组织方案,是指导施工准备和组织施工的全面性技术经济文件, 是现场施工的指导性文件。由于建筑产品的多样性,每项工程都必须单独 编制施工组织设计,施工组织设计经审批通过后方可施工。
1.2 施工组织设计的作用
1.2.1 指导施工前的一次性准备和工程施工全局的全过程
施工全过程是在施工组织设计的指导下进行的。首先,在接受施工任 务并得到初步设计以后,就可以开始编制建设项目的施工组织设计。施工 组织设计经主管部门批准以后,再进行全场性施工的具体实施准备。随着
施工图的出图,按照各工程项目的施工顺序,逐一制定各单位工程的施工 组织设计,然后根据各个单位工程施工组织设计,指导实施具体施工的各 项准备工作和施工活动。在施工工程的实施过程中,要根据施工组织设计 的计划安排,组织现场活动,进行各种施工生产要素的落实与管理,进行 施工进度、质量、成本、技术与安全的控制等。所以,施工组织设计是对 拟建工程施工全过程进行科学管理的重要手段。
2.2.2 项目管理的规划性文件
施工组织设计根据工程特点和施工的各种具体条件科学地拟定了施 工方案, 确定了施工顺序、 施工方法和技术组织措施, 排定了施工的进度; 施工人员可以根据相应的施工方法,在进度计划的控制下,有条不紊地组 织施工,保证拟建工程按照合同的要求完成。通过施工组织设计,可以使 我们对每一拟建工程,在开工之前就了解到它们所需要的材料、机具和人 力,并根据进度计划拟订先后使用的顺序,确定合理的劳动组织和施工材 料、机具等在施工现场的合理布置,使施工得以顺利地进行;还可以使我 们合理地安排临时设施,保证物资保管和生产与生活的需要。通过施工组 织设计,可以使我们大体估计到施工中可能发生的各种情况,从而预先做 好各项准备工作,清除施工中的障碍,并充分利用各种有利的条件,对施 工的各项问题予以最合理、最经济的解决。总之,通过施工组织设计,也 就把施工生产合理地组织起来了,规定了有关施工活动的基本内容,保证 了具体工程的施工得以顺利进行和完成施工任务。
1.3 施工组织设计的内容及分类
建筑工程施工组织设计的种类可以根据编制时间和编制对象的不同 来划分。根据编制时间的不同可分为:投标前编制的施工组织设计和中标 后、施工前编制的施工组织设计。
1.3.1 投标前编制的施工组织设计
投标前编制的施工组织设计是为了满足编制投标书和签订合同的需 要编制的,它必须对招标书所要求的内容进行筹划和决策,并附入投标文 件中。其内容包括:工程概况、施工方案、施工进度计划、主要技术组织 措施、其他有关招标文件所要求的内容。
1.3.2 中标后、施工前编制的施工组织设计
中标后、 施工前编制的施工组织设计是为了满足施工项目准备和实施 的需要。将根据工程规模的大小、结构特点、技术繁简程度和施工条件的 差异可分为三类:施工组织总设计、单位工程施工组织设计和分部分项工 程施工设计。
a )施工组织总设计:施工组织总设计是根据已经批准的初步设计或扩 大初步设计编制的, 是以整个建设项目或建筑群体为组织施工对象而编制 的全面规划其施工全过程各项活动的技术、经济的全局性、控制性文件。 主要内容包括:工程概况,施工部署与施工方案,施工总进度计划,施工 准备工作及各项资源需要量计划,主要技术组织措施及主要技术经济指 标,施工总平面图等。
b )单位工程施工组织设计:单位工程施工组织设计是在工程已列入年 度计划,进行施工图设计后,以单位工程(一个建筑物或构筑物)作为组
织施工对象而编制的,是用来指导其施工全过程各项活动的技术、经济的 局部性、指导性文件。
c )分部分项工程施工组织设计:分部分项工程施工组织设计一般是在 单位工程施工组织设计确定了施工方案后, 针对施工难度较大或技术较复 杂、工程规模大的分部分项为对象编制的,用来指导其施工活动的技术、 经济文件。
1.4 施工组织设计的编制
1.4.1 编制施工组织设计的依据
施工组织设计是根据不同的施工对象、现场条件、施工条件等主客观 因素,在充分调查分析的基础上编制的。不同类型的施工组织设计其编制 依据有共性,也存在着差异。施工组织总设计是编制单位工程施工组织设 计的依据;单位工程施工组织设计是编制分部(分项)工程作业设计的依 据。
1.4.2 编制施工组织设计的程序
施工组织设计的编制程序是指对其各组成部分形成的先后顺序及相 互间制约关系的处理。程序如下:
图 1 编制施工组织设计的程序图
在施工中,各项施工活动必须按照施工组织设计进行安排,各级施工 和技术领导应严格按照施工组织设计检查和督促各项工作的落实, 并做好 施工组织设计的交底工作,协调好施工组织设计与企业各类计划间的关 系,要有健全的组织管理系统,保证施工管理信息畅通 [3]。
1.5 进度计划的概念及作用
施工总进度计划是施工现场各项施工活动在时间上的体现。 编制的基 本依据是施工部署中的施工方案和工程项目的开展程序。 其作用在于确定 各个建筑物及其主要工种、工程、准备工作和全工地性工程的施工期限及 其开工和竣工的日期,从而确定建筑施工现场上劳动力、材料、成品、半 成品、施工机械的需要数量和调配情况,以及现场临时设施的数量、水电 供应数量和能源、交通的需要数量等等。
1.6 施工进度计划的编制
1.6.1 进度计划的编制依据
项目施工计划的编制依据,一是本项目的工程承包合同。合同中工期 的规定是确定工期计划值的基本依据,合同规定的工程开、竣工日期,必 须通过进度计划来落实。二是本项目的施工组织设计。这个资料明确了施 工能力部署与施工组织方法,体现了项目的施工特点,因而成为确定施工 过程中各个阶段目标计划的基础。三是企业的施工生产经营计划。项目进 度计划是企业计划的组成部分,要服从企业经营方针的指导,并满足企业
计划综合平衡的要求。除上述四点主要依据外,还应注意有关现场施工条 件的资料,主要包括施工现场的水文、地质、气候环境资料,以及交通运 输条件,能源供应情况,辅助生产能力等。 1.6.2 进度计划的编制程序
图 2 进度计划的编制程序
1.6.3 进度计划编制说明表
表 1 编制的进度计划表
第二章 射洪县新建法院审判楼工程的施工 组织设计研究与分析
2.1 工程概况及工程特点
2.1.1 建筑概况
该工程为地下 1层、地上 11层的剪力墙结构,总建筑面积 129000m 2, 建筑高度 34.10m (室外地坪至十一层女儿墙顶) ,地下 1层,层高 3.3m , 1至 11层住宅层高为 2.9m 。一、二、三、四单元为普通住宅,东边两层 为非配套公建设施,地下一层储藏。普通住宅每单元设有一座载人电梯一 座踏步式楼梯。
表 2 主要装修设计做法表
2.1.2 结构概况:
该工程结构体系为钢筋混凝土体系,结构类型为剪力墙结构。±0.00以上地上 11层,地下 1层。本工程基础设计采用板式筏形基础。地下室 底板砼厚度为 600mm 和 1000mm 。地下室外墙壁厚为 300mm ,配有内外两层 钢筋网。底板底和砼外墙均设有 SBS (3+3)聚脂胎卷材防水层,采用外防 外贴法。
结构用料
a )混凝土强度等级
表 3 混凝土强度等级表
b )钢材
1)钢筋:Ⅰ级钢筋 HPB235(φ) fy =210N/mm2 d≤ 12
Ⅱ级钢筋 HRB335(Φ) fy =300N/mm2 d =12
Ⅲ级钢筋 HRB400(Φ) fy =360N/mm2 d ≥ 14
2)焊条:HPB235级钢筋采用 E43;
HRB335级和 HRB400级采用 E50;
钢筋与型钢焊接随钢筋定焊条。
c )墙体工程:
1) 0.00以下的内隔墙为 200厚陶粒混凝土空心砌块, M5混合砂浆;
2)±0.00以上部分隔墙采用 200、 100厚两种;
3)所有分户墙不小于 200厚(混凝土墙除外) 。
4)所有户内隔墙为 100厚。
d )主要设计要求如下:
1)抗震设防烈度:8度;
2)结构抗震等级:二级;
e )混凝土抗渗标号、外加剂:
1)抗渗标号:地下室底板和外墙混凝土抗渗标号为 S6;
2.1.3 工程特点
该工程施工的技术要求高,工期紧,要按期交工必须科学合理的精 心组织,精心施工。土建施工、水电、消防、通讯及室内粗装饰工程穿插 同时施工,工作配合及关系协调是按期完成施工至关重要环节。该工程材 料涉及范围广、种类多,在防火、防水、防盗等工艺设计上新型材料使用 较多。
2.2 人员配备计划
2.3 工程的总体部署介绍及分析
2.3.1射洪县新建法院审判楼工程施工总体部署
(a )施工部署
组织建立工程项目部统一部署、统一指挥,实行项目经理负责制,明
确职责,责任到人。
(1)施工组织部署
组织施工以土建为主,安装及装饰工程配合施工,协调建设单位所指 定的各分包单位的分项工程施工。
整个工程分基础工程、主体工程(含水电安装工程) 、屋面工程、楼 地面工程、门窗工程和装饰工程、安装调试及了尾工程等。各分部分项工 程通过平衡协调及调度,紧密地组织成一体;总的施工部署遵循“先地下 后地上,先主体后装饰,安装与主体配合施工”的原则,重点抢基础与主 体工程,安装工程在整个土建工程施工过程中穿插进行,外装饰工程待主 体工程封顶验收后组织施工; 整个工程施工以关键项目——主体工程为主 要进度控制线,一切施工管理(人、材、物)必须首先满足该部分施工, 确保结构施工和楼地面施工进度计划的完成。
(2)资源配置
(a )剪力墙、梁、板所用模板均采用木模,支撑及顶撑采用优质碳 素钢 Q235碗扣架。
(b )施工现场的主要垂直运输机械:1台 80T-M 塔吊, 2台上人电 梯。
(c )外脚手架采用钢管脚手架(另编制专项施工方案) 。
(3)施工程序
施工程序:关键项目的施工采用重点集中和连续作业,非关键项目穿插进 行交叉作业的施工方法和顺序。施工顺序如下:
图 4 施工顺序图
(4)现场施工设一个土建施工队,安装、装璜、机务队各设一个专 业队,组织流 水作业;其他各专业队分组与土建队配合。地下室 按顶板变形缝进行分段施工,组织
流水作业。
(b )工期控制
合同要求工期为 420天,根据该工程特点,安排人力、物力,精心组 织精心施工,按工期要求竣工交付使用,具体控制点为:地下工程:约 40天;上部主体结构:约 125天; (包括冬期施工)装修:140天; (不包括 主体施工时穿插进行的装修)竣工了尾:30天。
(c )施工方案的选择
(1)±0.000以下基础的工程施工方案。 C15砼垫层:采用商品砼, 水平运输由人力斗车完成。钢筋砼地下室底板:先施工地下室底板,钢筋 现场制作安装,采用商品预拌砼,砼水平运输由输送泵完成。地下室墙、
梁板:墙模板采用胶合板模板,防水对销螺栓固定。梁板采用常规方法施 工。回填土:由场外选择优质粘土运至现场,采用工程铲车倒运至基坑, 部分为人力车倒运,机械分层夯实。
(2) 主体结构工程:主体结构施工阶段应充分合理安排, 具体部署方 案如下:模板工程:剪力墙配备一套模板 , 水平梁板结构配备三套模板, 垂直运输主要由塔吊进行吊运。 钢筋工程:均为现场统一制作, 塔吊吊运, 人工绑扎。砼工程:主要为商品预拌砼,垂直及水平运输主要由砼输送泵 及塔吊配合完成。 外墙脚手架:双排扣件式钢管脚手架自底层搭设至顶层, 架体外侧为安全网全封闭。
(3) 墙体砌筑结构和室内装饰施工方案。 在主体结构完成后开始, 从 下至上跟进施工,室内抹灰工程待分阶段结构验收后开始施工,其施工顺 序与墙砌体结构工程施工相同。
(4)外墙装饰工程待所有墙体砌筑完成后由上至下进行。
(5)门窗工程施工方案
所有门窗均按设计要求与专业厂家订购成品,现场安装。
(d )施工机械的选择
本工程地下室开始施工时,垂直及水平运输设 1台 80吨 /米塔吊,塔 吊基础外围砌 240砖墙至室外地面,用以保护塔基及电机,以保安全。塔 吊的布置应确保单体工程施工的作业面在塔吊的工作的半径内。 地下室工 程结构施工完毕,在主体结构及装修工程施工中,在楼附近各安装施工电 梯。钢筋加工等机械配备齐全。故选用的主要机械如下:
表 4选 用 主 要 机 械 设 备 表
2.3.2 对射洪县法院审判楼施工总体部署分析及修正
施工方案的选择是单位工程施工组织设计的核心。 施工方案确定的恰 当与否,直接影响单位工程的施工效果,施工方案的选择主要包括重要的 分部分项工程的施工方法、施工机械的选择、施工流向的确定、施工程序 和施工顺序等。施工组织总设计中要拟定一些主要工程项目的施工方案。 这些项目通常是建设项目中工程量大、施工难度大、工期长,对整个建设 项目的建成起关键性作用的建筑物(或构筑物),以及全场范围内工程量 大、影响全局的特殊分项工程。拟定主要工程项目的施工方案目的是为了 进行技术和资源的准备工作,同时也为了施工顺利开展和现场的合理布 置。其内容包括施工方法、施工工艺流程、施工机械设备 [4~6]。
施工部署包括施工程序、施工组织部署、资源配置、施工平面布置、 临建设施布置、材料堆场的布置等多方面内容,该施工组织设计过程中忽 略了施工平面布置。
a )施工平面布置的原则为:
1)按照前后兼顾的原则,合理分段,适时调整:分为主体结构施工 阶段和装饰阶段(安装)施工阶段,必要时做适当调整;
2)根据结构特点,合理布置大型设备,满足施工需要,保证施工安
全,在此基础上合理设置材料堆放场,尽可能避免二次搬运;
3)根据生产、生活区分原则,确保整个施工现场整洁、有序,各种 施工材料按要求分类堆放,并加以标识;
4)临时用电、用水的水平线路走向和垂直线路的走向布置规范、合 理;
5)遵守环境保护条例,避免环境污染;
6)施工现场按安全文明示范工地要求布置,力求美观,严格执行本 企业及地方管理规定。
b )临建设施布置
按照生产、生活区分开的原则,结合本工程的实际情况,场内设置生 产区、库房及办公室、门卫室、食堂、厕所,生活区均设置在场外。生产 区主要包括搅拌站、钢筋原材料堆放区、钢筋加工车间及半成品堆放区、 模板配置区、周转材料堆放区、砂石料堆场、水泥库、木工棚等。
c )材料堆场的布置
现场材料按照材料的性质及道路布置情况分类集中堆放。 在整个施工 过程中, 将根据施工总进度计划, 按需要有组织、 有计划地组织材料进场, 凡进场材料,必须按照平面布置所划分区域堆放。
2.4 工程进度计划分析
3.4.1 工程总进度计划分析
(a )施工总进度计划
编制施工总进度计划的基本要求是保证拟建工程在规定的期限内完
成;迅速发挥投资效益;保证施工的连续性和均衡性;节约施工费用。编 制施工总进度计划时,应根据施工部署中建设工程分期分批投产顺序,将 每个交工系统的各分项工程分别列出, 在控制的期限内进行各项工程的具 体安排。当建设项目的规模不大时,各交工系统工程项目不多时,也可不 按分期分批投产顺序安排,而直接安排总进度计划 [7~9]。
施工总进度计划编制的步骤包括:分期分批建设工程项目的划分以及 工程量的计算,单位工程施工期限的确定,各单位工程竣工时间的确定和 相互之间的搭接关系,进度计划的安排等 [8]。
(b )施工总进度计划的实施
施工总进度计划主要起控制总工期的作用, 施工进度计划的实施实际 上是进度目标的过程控制,是 P-D-C-A 循环的 D 阶段。项目的施工进度计 划应通过编制年、季、月、旬、周施工进度计划实现。年、季、月、旬、 周施工进度计划应逐级落实,最终通过施工任务书由班组实施。在这一阶 段中主要作好以下工作:
(1)编制并执行时间周期计划。
周期计划包括年、季、月、旬、周进度计划。该计划落实施工进度计 划,并以短期计划落实调整并实施长期计划,作到短期保长期,周期保进 度,进度保目标。
(2)用施工任务书进把计划任务落实到班组。
施工任务书是几十年来我国坚持使用的有效的管理工具, 是管理层向 作业人员下达任务的好形式,可用来进行作业和核算,特别有利于进度控 制, 故应当坚持使用。 它的内容包括:施工任务单, 考勤表和限额领料单。 (3)坚持进度控制应作好以下工作。
跟踪监督并加强调度,记录实际进度,执行施工合同对进度控制的承 诺跟踪进行统计和分析,落实进度控制措施,处理进度索赔,确保资源供 应进度计划实现等。
(4)加强分包进度控制措施。
由分包人根据施工进度计划编制分包工程进度计划并组织实施; 项目 经理部将分包工程计划纳入进度控制范畴; 项目经理部协助分包人解决进 度控制中的相关问题。
(5)施工进度计划检查依据施工进度计划的实施记录。
检查内容包括:实际完成和累计完成工程量,实际参加施工的人数、 机械数及生产效率, 机械台班数及其原因分析, 进度偏差及进度管理情况, 影响进度的特殊原因及分析。
(6)施工进度计划调整的依据是施工进度计划检查结果。
调整的内容包括:施工内容工程量起止时间、持续时间、工作关系和 资源供应。调整进度计划应采取科学方法,如网络计划计算机调整方法, 并应编制调整后的施工进度计划。
3.4.2 工程月进度计划分析
施工总进度计划、单位工程施工进度计划、分部分项工程施工进度计 划是按整个项目或单位工程编制的,带有一定的控制性,但还不能满足施 工作业的要求,实际作业时是按月(旬、周)作业计划和施工任务书执行 的 [2]。另外,施工进度计划是施工前编制的,其内容还比较粗,而且现 场情况又是在不断变化的,因此执行中还必需编制短期的、更为具体的执 行计划,月(旬、周)施工进度作业计划。 月(旬、周)施工进度作业 计划要明确本月(旬、周)应完成的各项施工任务,完成计划所需要的各
种资源量,提高劳动生产率和增产节约的措施。作业计划的编制还应该进 行不同的施工项目之间同时施工的平衡协调; 符合施工项目进度计划的期 限;施工项目的分解必须满足指导施工作业的要求、细分到工序、明确进 度日程。
月进度计划的实施关系到工程总进度计划,若月进度计划不能实现, 那么工程的总进度计划必将受到影响,若月进度计划调整合理,那么不会 影响到总的进度计划。
针对本工程,需进行的分项工程名称有:C20保护层、基础放线、地 下室底板钢筋绑扎、浇筑地下室底板砼、柱、墙钢筋绑扎、柱、墙模板、 柱、墙砼浇筑、地下室顶板模板、地下室顶板钢筋、地下室顶板砼浇筑、 一层柱墙钢筋、一层柱墙模板、一层柱墙砼浇筑、一层顶板模板。本工程 是 D1、 D2座同时进行,采用的是流水组织方式,由进度计划表中可以看 出,这种流水方式使建筑安装生产活动有节奏的、连续和均衡的进行,这 样就加快了各专业施工队的施工进度,减少了时间间歇,特别是相邻专业 施工队,在开工时间上,最大限度地、合理地搭接起来,充分地利用了工 作面,做到了尽可能早的开始工作,从而达到缩短工期的目的。在 D1座 进行基础放线时 D2座的地下室底板钢筋就进行了绑扎,这样两栋楼工程 同时施工,缩短了工期,使人员、机械不闲置,也充分发挥了施工机械和 劳动力的生产效率, 这种施工方式没有窝工的现象, 增加了有效劳动时间。 此外,这种作业方式降低了工程成本,提高了施工企业的经济效益,因为 流水施工节约了工程的直接费用,减少了临设工程费和施工管理费。流水 施工资源消耗均衡,便于组织物质供应工作,储存合理,利用充分,减少 了各种不必要的损失,节约了材料费;生产效率高,节约了人工费和机械
使用费;材料和设备合理供应,减少了临设工程费用;降低了施工高峰人 数, 工期缩短, 工人的人数减少, 节约了施工管理费和其他的有关费用 [10~ 12]。 本工程采用的这种流水方式, 在施工过程中即使由于各种原因使工期 延误,但如果组织了合理的流水施工那么不会影响到工期的变化。 第三章 射洪县法院审判综合楼程进度研究 及对策
通过对本工程的月进度计划、总进度计划进行分析,由于本工程开工 时间不长,所以月进度按计划实施,但未来的多种因素有可能导致工期延 误,所以对进度计划进行调整势在必行。
3.1 施工总进度延误原因分析及解决方案
为了对工程项目的施工进度有效地控制, 必须在施工进度计划实施之 前对影响工程项目工程进度的因素进行分析, 进而提出保证施工进度计划 实话成功的措施,以实现对工程项目施工进度的主动控制。影响工程项目 施工进度的因素有很多,该工程在施工过程中由于自然因素、图纸因素、 施工方施工组织不当或甲方的因素造成工程工期延误。
3.1.1 原因分析 及解决方案
(a )施工条件、自然因素的影响
本工程在施工过程中,遭遇到天气变化、雨水、地震等因素的影响, 影响到工程施工进度, 而承包单位由于自身施工组织不当没有完全克服不 利影响,造成了工期延误,虽然在日后的施工中尽量弥补由此造成的工期
延误,但自然因素的影响不可避免,因此可以向甲方进行必要的索赔。 (b )工程建设相关单位的影响
影响工程项目施工进度的单位不只是施工承包单位。事实上,只要是 与工程建设有关的单位(如政府有关部门、业主,设计单位、物资供应单 位、资金贷款单位以及运输、通讯、供电等部门等) ,其工作进度的拖后 必将对施工进度产生影响。在工程施工的过程,甲方的供料不当影响工程 施工进度。本工程开发商为了集中整合、利用社会资源,集中采购便于节 约成本、节约投资,也为了保证工程项目所用主要材料、设备质量和进场 时间,在工程施工合同中约定了甲方供料的内容。甲方供料一般主要是指 由开发商供应钢材、水泥、木材、商品混凝土等主材、安装工程的未计价 材,以及电梯、水泵、变配电、空调等主要设备等。本工程开发商甲方供 料内容越来越多、越来越细,甲方供料的交接、验收、保存、结帐等方面 的环节,加大了开发商的工作量,造成承包方的依赖性,而且承包方将工 程质量、工期责任归结于甲方;甲方供料的质量问题及供应滞后,给施工 方工程质量问题、工期拖延造成理由,而且会产生承包商索赔,加大工程 项目管理和项目成本。故甲方供料的范围、方式选择和实施效果不当延误 了工程正常的施工进度。因此,控制施工进度仅仅考虑施工承包单位是不 够的,必须充分发挥监理的作用,协调各相关单位之间的进度关系。而对 于那些无法进行协调控制的进度关系, 在进度计划的安排中应留有足够的 机动时间。
(c )物资供应进度的影响
施工过程中需要的材料、构配件、机具和设备等如果不能按期运抵施 工现场或者运抵施工现场后发现其质量不符合有关标准的要求, 都会对施
工进度产生影响。质检员的任务就是检验材料是否合格,在工程施工中难 免会因为材料供应不足或质量问题造成工期延误,因此,项目进度控制人 员应严格把关,采取有效措施控制好物资供应进度。
(d )资金的影响
工程施工的顺利进行必须是足够的资金作保障。一般来说,资金的影 响主要来自业主,或者是由于没有及时给足工程预付款,或者是由于拖欠 了工程进度款,这些都会影响到承包单位流动资金的周转,进而殃及施工 进度。项目进度控制人员应根据业主的资金供应能力,安排好施工进度计 划,并督促业主及时拨付工程预付款和工程进度款,以免因资金供应不足 而拖延进度,导致工期索赔。
(e )设计变更的影响
在施工过程中,出现设计变更是难免的,或者是由于原设计有问题需 要修改,或者是由于业主提出了新的要求。项目进度控制人员应加强图纸 审查,严格控制随意变更,特别对业主的变更要求应引起重视。
(f )各种风险因素的影响
风险因素包括政治、经济、技术及自然等方面的各种预见的因素。政 治方面的有战争、内乱、罢工、拒付债务、制裁等:经济方面的有延迟付 款、汇率浮动、换汇控制、通贷膨胀、分包单位违约等;技术方面的有工 程事故、试验失败、标准变化等;自然方面的有地震、洪水等。
(g )承包单位自身管理水平的影响
施工现场的情况千变万化, 如果承包单位的施工方案不当, 计划不周, 管理不善,解决问题不及时等,都会影响工程项目的施工进度。
3.2 工程月进度及施工工期拖延原因分析及解决方案
4.2.1 本工程 4月份实际完成情况与计划进度比较分析原因
( a)进度分析
4月施工计划与施工实际完成情况相比, 施工实际完成工程进度与计划 进度相比,推迟了 10天。未完成计划的原因主要有以下几点:
(1)图纸变更较多。
(2)施工方的材料供应迟迟不到位。
(3)塔吊迟迟未进场,基础钢筋的绑扎靠人工搬运。
(4)基础砼浇筑由于商混供应的原因停工 3天。
(5)由于管理人员配备不齐全,造成管理环节脱节。
(6) 土方工程施工组织不利, 致使土方工程到本月 11日才全部完工, 开挖用了 20 多天,而且连续几天的多雨天气,使验槽工作一拖再拖达 一周的时间,更重要的是施工图纸的变更结果未出,所以造成了形象进度 远没有达到计划进度要求的结果。
经分析得出:本工程致使工期延误是施工方原因造成的。因此,一切 损失由承包商自己承担。如果由此导致业主发生了额外费用,承包商应补 偿业主的这类损失。设备监理工程师应根据合同条件,公平合理地确定造 成进度拖延的原因是承包商原因,还是非承包商原因,这对承包商和业主 都十分重要。设备监理工程师应依据合同和事实,充分与双方进行协商并 最终确定相应的工期和费用责任。
(b )解决方案
(1) 项目经理在施工月、旬作业计划实施前要进行交底,并对施工队 和分承包方下达作业计划任务书。施工队(分承包方)应根据施工月、旬 作业计划的任务书要求,把月、旬作业计划按分部分项工程下达给各专业 技术(工长)人员和相关管理人员。各专业技术(工长)人员应编制月、 旬施工任务单,将月、旬作业计划任务落实到施工作业班组。
(2) 应进行跟踪监督,当发现作业计划执行受干扰时,应采取相应措 施,重要单位工程或关键工序的施工时,专人或施工队计划人员应进行重 点跟踪监督,要做好施工记录,在施工月、旬作业计划图上进行实际进度 记录,每周进行作业计划与实际进度的比较分析,跟踪形象进度,对工程 量、总产值、耗用的人工、材料和工程设备、机械台班等的数量进行统计 与分析。
(3) 掌握重要单位工程和关键工序的施工作业计划的实施情况, 做好 施工资源调度工作,做好与相关方的协调工作,协调施工中的各个环节、 各个专业工种之间相互配合关系。
(4)施工月、旬作业计划检查应采取日检查的方式进行,施工作业班 组施工任务单完成后,由施工队进行检查验收,月末由项目经理部对施工 队(分承包方)月、旬作业计划任务书执行情况进行检查验收,进行实际 完成形象进度与施工月、旬作业计划的对比、分析、总结,提出存在问题 和改正意见。
3.2.2 对于工期延误解决方案
为了使本工程按进度计划竣工,并交付建设单位投入使用,进度计划 要编排紧凑 ,尽量满足建设单位的要求,与土建队伍精心施工、相互配合, 应采取以下措施:
(a )加强工程进度的控制
图 5 进度控制程序图
(b)向管理要工期
(1)具备科学的管理体系和管理方法是一支现代化施工队伍的重要条 件,它是本工程工期缩短的先决条件和重要保障。公司上下必须完善各项 管理制度和管理方法,用国内外最先进的管理模式来管理工程项目部 [13], 要求在项目部建立一支现代化的施工队伍,管理机构配备齐全,专业分工 明确;施工期间每三天一次召开工程项目部内部协调会,就施工中的有关
生产、技术、质量、安全及材料等各方面的问题进行协调,每次协调会形 成纪要,下次协调会检查落实情况,以确保不影响进度;每周参加由建设 单位组织,监理单位、施工单位及各有关专业施工队伍参加的工程协调会 议。主要协调土建、消防、水电安装、弱电等专业工程在工期、质量、人 员穿插等施工配合;协调同外界有较大影响的横向关系,为工程提供一个 良好的施工环境,避免大的干扰。当出现设计变更或工程量增减时,项目 部应以合同形式明确双方协作配合要求,以免影响施工进度;立足工程全 局,按工程形象进度计划对工程的实施进度进行监督,分析可能影响工程 进度的各种因素,做到有问题及时提出,及时解决,使工程始终处于良性 循环中;及时妥善处理和监督工程中遇到的突发性事件,避免影响本工程 正常进度;施工总进度目标是从总的方面对工程建设提出的工期要求。在 施工当中,则是通过对最基础的分部、分项工程的施工着手实行进度控制 的,并以此来保证各单位工程进度控制目标的实现。因而需要将总进度目 标进行一系列的从总体到细部,由高层次到基础层次的层层分解,一直分 解到在施工现场可以直接调度控制的分部分项工程或工序的施工为止 [13~ 15]。
(2)确定项目部一级管理的任务和职责:劳动力、机械设备、周转材 料以确保工程进度的前提,必须分阶段制定计划,按计划配足,并合理配 置和使用,做到稍有富余,但又要避免窝工等浪费;按工程进度计划,安 排各工种搭接,工期切实做到周密安排。执行各分部分项工程进度计划, 编制周进度计划和周工程量报表,并认真执行按期完成;对各类生产班组 进行计划进度、生产技术、质量安全、文明施工等交底工作,并认真做好 各种台帐;劳动力优化结合,在结构施工中安排好梁板结构施工等关键工
作,对必须连续施工作业的分部分项工程安排好加班人员;做好各分部分 项的检查、评定和验收,及时通知建设单位、公司工程及监理单位参加工 程的各种隐检。
(c)加大物资材料、机械设备和劳动力的投入
(1)强大的投入量是保证工期的前提,必须精心、实际地编写单项工 程施工组织设计,对重要分部工程由项目部制定切实可行、有针对性的单 项施工方案。做到生产周有作业计划,根据计划落实劳动力、材料、设备 的进场,确保全部到位 [16~18]。
(2)公司仓库内已备足了本工程需用的大部分机械设备,将按需运往 施工现场。因此,机械设备不会本工程的施工工期。
(3)在工程结构和装修工程施工期间,可投入相当一部分劳动力加夜 班,这样可缩短很多工期,从而也为本工程早日竣工奠定基础。
结 论
建设工程项目施工组织设计是从工程施工全局出发, 根据工程的特点 和设计图纸,按照工程项目的客观 规律 及项目所在地的具体施工条件和 工期要求,统筹考虑施工活动中人工、材料、机械、资金和施工 方法 等 五大要素,对全部工程的施工工艺、施工进度和相应的资源消耗等做出 科学 合理的安排,为施工生产活动的连续性、协调性、均衡性和 经济 性 提供最优方案,以最少的资源消耗取得最大的经济效益而编制的指导性 文件。它起着指导施工准备工作,全面布置施工活动、控制施工进度、 进行劳动力和机械调配的作用,同时对施工活动内容各环节的相互关系 与外部联系,确保正常施工秩序起着有效的协调作用。
通过对此次论文的撰写,让我们了解到施工组织的重要性,及编制 施工组织设计的重要性。 一份完整的施工组织设计, 进度计划必不可少, 一份好的施工组织设计对进度计划的编制显得尤为重要。本论文的主旨 是对该工程土建部分的施工进度计划进行分析,通过在工程中的实习, 找出问题,发现问题,并且运用观点对此项工程的施工组织设计进行分 析,对造成工程工期延误的客观与主观原因进行分析,并结合论点解决 问题,并画出合理的施工进度计划。
多年来,我国建筑工程项目在已形成了一套完整的、符合我国国情 的编制施工组织设计的方法。但是,随着我国改革开放步伐的加快,随 着 社会 经济的不断 发展 ,工程规模日益庞大,新材料、新工艺不断出现,
施工技术也更加先进和复杂,以及我国建设工程项目管理体制改革的深 入,建设工程的有关 法律 、法规日益建立,特别是我国在建设工程管理 中已全面实施市场准入制、项目法人制、招标投标制、建设监理制、工 程质量监督制和工程合同管理制,传统的公路建设项目施工组织设计管 理制度并没有系统地上升到工程项目管理 理论 和现代管理科学来认识, 还存在着诸多违背现代管理科学原理的弊端,需要改革才能适应这种变 革,这已是势在必行了。
参 考 文 献
1 徐悦,建筑施工组织 . 北京:机械出版社, 2006
2 郭庆阳 . 建筑施工组织 . 中国电力出版社, 2003
3 张立新 . 土木工程施工组织设计 . 中国电力出版社, 2004
4 丛培经,张书行 . 工程项目管理 . 第三版 . 中国建筑工业出版社, 2006
5 闫文周 . 工程项目管理 . 北京机械出版社, 2006
6 金同华,施工项目管理 . 北京:机械出版社, 2006
7 王洪,陈健 . 建设项目管理 . 北京机械出版社, 2003
8 齐宝库,工程项目管理 . 大连理工大学出版社, 1999
9 工程设计与施工项目管理(美)奥博兰德(Oberlender,G.D. ) 著,毕星等译、—北京:清华大学出版社, 2006、 2
10 刘钟莹等 . 建筑工程施工管理 . 第一版 . 东南大学出版社, 2005 11 王丽霞 . 项目施工组织与管理 . 郑州大学出版社, 2003
12 焦红 . 现代项目施工技术与项目管理 . 同济大学出版社, 2007.04 13 朱红燕 . 建筑工程施工技术交底 . 地震出版社, 2003
14 王宗昌 . 建筑施工细部操作质量控制 . 中国建筑工业出版社, 1998
15 詹炳根,殷为民 . 工程建设监理 . 中国建筑工业出版社, 2003 16 Geneva. Handbook on Exporting Technical Consultancy services from Countries in the Asia and Pacific Region .International Trade Centre,1991
17 Lasser, Handbook of accounting methods, D.Van Nostrand Company.INE,1993
18 LIU Jun ’ e CHEN Yan SUNJin , Fuzzy Comprehensive Evaluation of Investment Environment of Real Estate[J]. 2003:347-351
致 谢
随着论文的完成,我的大学生活也随之结束,新的生活,工作即将 开始。在这几个月的论文撰写过程中,我学到很多,不只课本知识面的 充实,还有很多为人处事的态度。论文是毕业生必不可少的一部分,但 并不是全部, 论文的撰写是对近半年工作的总结及肯定。 虽然过程艰苦, 但坚持就是一种胜利。
在论文的设计和完成过程中,我的指导老师刘晋老师给予了我很大 的帮助。刘老师一再地为我解答毕业论文设计中的疑问,孜孜不倦地进 行指导,同时对我的毕业论文提出了许多宝贵的意见,才使我最终顺利 地完成了毕业论文。在此,谨向刘老师表示深深的敬意和衷心的感谢。 感谢在我毕业设计过程中给予我帮助和支持的同学们,特别要感谢 湖北省麻城市第四建筑公司梦之都花园二期工程项目部的领导及同事, 他们给我提供了大量的资料信息,我的毕业论文的圆满完成与你们的支 持和帮助是分不开的。
论文的完成是新的生活的开始,我会珍惜论文撰写过程中的点点滴 滴,无论对与错都是一种历练,从开始进入课题到论文的顺利完成,同 学们互相帮助,在此,对于帮助过我的同学们表示真挚的感谢。
作文二:《土木工程毕业设计》21500字
摘 要
本工程地下二层为为自行车库,层高 3.4米;地下一层为自行车库、配电间等,层 高 3.6米;地下夹层为设备管道层,层高 2.1米;地上为住宅,共 27层,层高均为 2.9米。
本设计主要包括各阶段施工方法及施工要点。本工程施工现场管理标准要求非常 高,我们将按照建设单位创建“优质工程、精品工程”的指导精神,全力配合发包人对 于 4#地项目销售和品牌形象建设的需要以及全面响应施工合同的要求, 我单位将通过各 项管理措施确保本标段施工现场管理达到“北京市安全文明工地”标准,确保获得“北 京市安全文明工地”称号。
关键词:
安全文明、施工部署、平面管理
Abstract
The two layer underground garage for themselves, the height of 3.4 meters; underground layer of their own garage, power distribution room, the height of 3.6 meters; underground layer of pipeline equipment layer, the layer is 2.1 meters tall; land for residential, a total of 27 layers, which is 2.9 meters tall.
This design mainly includes the design of the various stages of construction methods and key points of construction. The requirements of the project construction site management standards are very high, we will be in accordance with the construction units to create
Safe and civilized construction management, deployment, plane
目录
第一章 编制依据 ...................................................... 1 1.1工程合同 ...................................................... 1 1.2施工图纸 ...................................................... 1 1.3主要规程、规范 ................................................ 1 1.4主要标准 ...................................................... 4 1.5主要图集 ...................................................... 5 1.6主要法规、规定 ................................................ 5 1.7其它 .......................................................... 6 第二章 工程概况 ...................................................... 7 2.1总体简介 ...................................................... 7 2.2建筑设计简介 .................................................. 8 2.3结构设计概况 .................................................. 9 2.4工程典型的平、剖面图 ......................................... 10 住宅楼剖面 2.5 本工程特点及难点 .................................. 11 第三章 施工部署 ..................................................... 13 3.1施工管理目标 ................................................. 13 3.2施工部署原则 ................................................. 13 3.3施工组织机构及职能分工 ....................................... 16 3.4 主要项目工程量表 ............................................ 25 3.5施工进度计划 ................................................. 25 3.6原材料、构配件、设备的加工及采购计划 ......................... 26 3.7主要劳动力计划 ............................................... 29 3.8协调与配合 ................................................... 32 第四章 施工准备 ..................................................... 36 4.1 技术准备 .................................................... 36 4.2 生产准备 .................................................... 44 第五章 主要施工方法 ................................................. 49 5.1流水段划分 ................................................... 49 5.2大型机械设备选择 ............................................. 50
5.3主要施工方法 ................................................. 51 5.4工程季节性施工方案 ........................................... 71 第六章 施工总平面图 ................................................. 75 6.1总平面布置 ................................................... 75 6.2总平面管理 ................................................... 76 结束语 ............................................................ 77 致谢 ................................................................ 78 参考文献 ............................................................ 79 附录 ................................................................ 80
第一章 编制依据 1.1工程合同
1.2施工图纸
1.3主要规程、规范
1.4主要标准
1.5主要图集
1.6主要法规、规定
1.7其它
第二章 工程概况
2.1 总体简介
序号 1 2 3 4 项 工程名称 工程地点 建设单位 设计单位 勘察单位 5 6 7 8 9 10 11 12 监理单位 质量监督单位 施工总承包单位 结构劳务分包单位 建设规模 资金来源 合同承包范围 结算方式 目 内 容
朝阳区来广营乡清河营村住宅及配套、 商业金融 (4 号地)项目 2 号住宅楼 朝阳区来广营乡清河营 4#地 北京世纪鸿城置业有限公司 华通设计顾问工程有限公司 北京市勘察设计研究院有限公司 北京东方华太建设监理有限公司 北京朝阳区质量监督站 北京城建北方建设有限责任公司 江苏盐城二建集团第一工程有限公司 24184 ㎡ 甲方自筹 土建、装饰、电气、给排水、通风空调、电梯 预算加变更洽商 于 2015 年 03 月 01 日开工,2017 年 1 月 27 日竣
13
合同工期
工验收,2017 年 2 月 28 日完成竣工备案,总工期 698 日历天。
14
创优目标
确保北京市结构“长城杯”。
7
2.2 建筑设计简介
序号 1 项目 内 容 地下二层为为自行车库,层高 3.4 米;地下一层为自行车库、 建筑功能 配电间等,层高 3.6 米;地下夹层为设备管道层,层高 2.1 米; 地上为住宅,共 27 层,层高均为 2.9 米。 总建 2 3 筑面积 层数 24184m2 地 上 ±0.000 4 建筑高度 檐口高 度 总体尺 5 6 7 8 平面尺寸 建筑防火 建筑层高 外装修 寸 一类 地下 地上 外墙装修 顶棚 地面工程 9 内装修 内墙装修 踢脚 门窗工程 屋面保温 10 保温工程 外墙保温 外门窗 其中地下 建筑面积 27 层 33.60 0m 1626m2 地 下 最大基坑深 度 80m 2层 -10.21m
南北向 18.65m;东西向 62.45m 耐火等级 一级
地下二层:3.40m;地下一层:3.60m;夹层:2.10m。 2.9m 面砖、干挂石材、涂料 水性耐擦洗涂料顶棚、刷涂料顶棚 防滑地砖楼面、水泥楼面、水泥砂浆地面、细石混 凝土地面 耐水腻子墙面 地砖踢脚、水泥踢脚 防火门、木门、安全户门、推拉门、铝合金中空玻 璃窗 60 厚挤塑聚苯板 70 厚挤塑聚苯板 选用铝合金断桥隔热中空玻璃门窗 防水等级Ⅰ级,设两道防水,一道采用防水混凝土 自防水, 其抗渗等级 P8; 另一道防水为结构外包 4+3 厚 SBS 改性沥青防水卷材, 侧墙防水保护层为 30 厚 挤塑聚苯板。
8
11
防水工程
地下室
屋面
防水等级二级,采用 3+3 厚 SBS 改性沥青防水卷材
卫生间及楼 1.5 厚单组分聚氨酯防水涂料 层防水
2.3 结构设计概况
序号 1 2 3 4 5 6 7 8 9 项 目 结构体系 结构安全等级 结构抗震等级 基础设计等级 结构层数 抗震设防分类 场地类别 环境类别 结构形式 剪力墙结构 二级 地下二、一层剪力墙:三级 地下夹层及以上剪力墙:二级 乙级 设防烈度为 8 度。 Ⅲ类 与土壤接触的地下室外墙、板及基础为二 b 类,卫生 间、厨房为二 a 类,其它为一类。 基础结构形式 主体结构形式 CFG 桩复合地基,箱型基础 剪力墙结构 设计使用年限 50 年 地下室:地下 2 层;地上:27 层。 内 容
10
混凝土强度等级
垫层 C15;基础底板、基础梁:C35; 主体结构(柱、墙、梁、板)-2~6 层:C35;7 层及以 上:C30; 楼梯及其他:随楼板; 后浇带:C40; 基础底板、地下室外墙抗渗等级:P8。 底板 900mm 180、200、250、300mm 120、180mm 表4
11 12
结构断面尺寸(mm) 砌体工程
剪力墙 楼板
轻质条板隔墙、轻集料混凝土空心砌块填充墙
9
2.4 工程典型的平、剖面图
2.4.1 地下室平面图
2 号楼地下室平面图 2.4.2 标准层平面图。
2 号楼地上平面图
10
2.4.3 典型剖面图。
住宅楼剖面
11
2.5 本工程特点及难点
2.5.1 现场布置方面 2.5.1.1 现场安全文明施工要求高 本工程施工现场管理标准要求非常高,我们将按照建设单位创建“优质工程、精品 工程” 的指导精神, 全力配合发包人对于 4#地项目销售和品牌形象建设的需要以及全面 响应施工合同的要求,我单位将通过各项管理措施确保本标段施工现场管理达到“北京 市安全文明工地”标准,确保获得“北京市安全文明工地”称号。 2.5.1.2 开工规模大,总包单位多,协调配合难度大 群塔作业现象相互影响较大,在我方的施工区域里,1#、2#楼的塔吊存在着交叉 作业,2#、3#楼的塔吊存在交叉作业,在施工过程中,群塔作业及塔吊的锚固及提升 需要统一协调和组织安排,以确保安全作业提高施工效率。 2.5.1.3 施工场地狭小、平面布置困难,相互影响施工的因素多 施工现场临设用地面积较小,基础施工阶段,现场只有 2#、3#楼北侧有一部分场地 和车库东侧有一部分场地, 工程同时施工, 所需施工材料和周转材料数量大, 材料堆场、 施工机械布置、车辆调度受限制较大,材料、机械二次搬运量大,要合理安排施工顺序 与临设布置;结构施工时周转材料、钢筋、混凝土的运输等也需要合理规划和组织。 2.5.3 技术方面 2.5.3.1 外装饰结构较多 2 号住宅工程结构外挑构件及外装饰结构较多:结构外挑的空调板、 凸窗窗套板、 顶 层阳台板以及外装饰用层间腰线板等,给测量放线、模板施工、外脚手架施工等带来很 大困难。 2.5.3.2 住宅同时开工,群塔施工协调任务重 设置 1 台塔吊(型号为 FO/23B),施工过程中 2#楼和 3#楼塔吊之间相互覆盖范围形 成作业范围的交叉, 1#楼与 2#楼之间也存在塔吊作业范围的交叉, 如何保证群塔作业的 安全是本工程的一个重点和难点。 2.5.3.3 本工程须经历两个冬期施工和一个雨期施工。 根据工程形象进度,考虑季节性对施工的影响。统筹兼顾,综合安排施工作业,受 季节性影响的施工工序应尽量避开冬、雨期,以保证工程质量。
12
第三章 施工部署
3.1 施工管理目标
3.1.1 质量管理目标 质量标准:合格; 质量目标:确保 2 号住宅楼工程获得北京市结构“长城杯”。 3.1.2 工期管理目标 总工期为 698 日历天,2015 年 3 月 01 日开工,2017 年 1 月 27 日竣工。 3.1.3 安全管理目标 杜绝火灾、爆炸事故和重大机械设备安全责任事故,年度内杜绝发生因工死亡责任 事故,严格控制重伤、轻伤事故。年度内因工死亡责任事故为零,重伤事故频率小于万 分之五,轻伤事故频率小于千分之三,杜绝食物中毒事故。 3.1.4 文明施工管理目标 确保达到“北京市绿色文明安全工地”标准,遵循 ISO14001:2004 标准,全过程 实现“绿色施工”。 3.1.5 消防管理目标 始终贯彻“预防为主,防消结合”的消防工作方针,认真执行有关法规,强化消防 工作管理,杜绝火灾事故,避免火警事故。 3.1.6 环境保护管理目标 现场施工噪声、废水排放、扬尘污染、固体废弃物排放符合标准要求;有毒有害废 弃物分类存放、集中消纳;降低能源、资源消耗。 3.1.7 回访与维修管理目标 履行施工合同约定和《工程质量保修书》中的承诺,工程竣工正式移交后成立由各 专业人员组成的专修队伍,实行“24 小时服务”,让业主满意。
3.2 施工部署原则
为实现工程建设“工期、质量、安全、环保、消防”等方面的管理目标,施工将遵 循“应用合理的施工专业技术,选用成建制有同类工程施工经验的劳务队,合理投入机 械设备,科学安排施工顺序,精心施工,并遵循先地下后地上,先结构后维护,先主体 后装修,先土建后专业的常规施工顺序,结合质量创优,加强工序样板控制,做好阶段 性工作验收,达到“优质、安全、按期竣工”的原则进行施工总体部署。
13
3.2.1 施工部署总原则 (1)保证工程质量的原则 本工程质量目标确保北京市结构“长城杯”,项目经理部负责编制项目质量计划及 项目质量管理办法,质量计划包含保证工程质量的各个要素的工作计划、质量要求、工 作流程,是项目管理的工作质量保证措施;项目质量管理办法明确了项目部对各分部/ 分项工程具体的管理措施,使施工质量始终处于受控状态。 落实施工组织设计、施工方案的执行检查措施:施工组织设计、施工方案一经审核 批准,即作为本项目施工纲领性文件,必须得到严格执行。如果文件修改,必须编制修 改方案,填写修改记录,由原审核人对修改的条目进行审核,由原审批人审批后方可执 行。 (2)满足平行流水、交叉施工、动态划分施工区段的原则 根据工程特点及周边环境条件,综合考虑工程工期、质量、劳动力、周转材料、大 型机械、临建设施等资源投入情况,组织分阶段分重点进行施工。施工期间,在平面上 分施工区段,竖向上分流水段,相互交叉作业,合理利用施工步距。随着施工阶段和工 程体量的变化,动态地调整施工区段和规划施工现场平面布置。合理组织,保证施工的 连续性、均衡性、节奏性,做好分阶段验收安排,在结构施工期间将提前插入二次结构、 装修、机电管线安装的施工。尤其注重保障分包施工项目的工序穿插,提前做好各方面 的施工准备。 (3)坚持临设阶段性、适用性、灵活性及可改造性兼顾的原则 科学合理布置施工临时设施、运输道路、临时用水、临时用电等,立足集中管理、 方便运输、可移动性强,以施工总进度计划为依据进行阶段性调整,为各专业分包提供 服务场地,最大限度地减小临时设施占地,做到投入最低,收效最大,经济适用。在该 工程中,一些跨越周期较长的临设,如办公区、试验室、料库等设施在整个施工期间都 将利用,因此布置在现场不受施工影响的部位;而钢筋加工厂、模板加工厂、周转材料 堆放区等随工程进度变化较大的场区,将动态地布置。 结构及装修施工阶段,钢筋、模板、周转材料堆放在基坑以外的场地,到装修施工 阶段时,地下车库已回填后形成可利用场地,根据实际情况再二次布置现场。 (4)本着依靠科技促进生产的原则 本工程大力提倡建筑业“四新”技术的应用,大力开展科技创新,开展“QC”活动。 3.2.2 工程实施程序总体安排 总体流程:进场→工程定位→土方开挖和基坑支护→CFG 桩施工→垫层及防水保护
14
墙施工→底板防水及保护层施工→基础及主体结构施工、专业预埋→土方回填→主体结 构施工→二次结构、水电管道安装、屋面施工、外装修→室内装修、设备安装及调试→ 有关系统按专业验收、资料整理汇总→竣工报验。 3.2.3 工程实施步骤 根据施工特点,将本工程划分为五个施工阶段,即第一阶段施工准备阶段;第二阶 段地下结构施工阶段;第三阶段地上主体结构施工阶段;第四阶段装修及设备安装施工 阶段;第五阶段竣工调试、清理、验收阶段。 1) 施工准备阶段(2015 年 03 月 1 日至 04 月 15 日) 由于我单位进场前后土方开挖、护坡、降水、CFG 桩等工程已经由业主指定的分包 单位基本完成,因此施工准备时间短。该阶段的工作重点是:①组织图纸会审;②进行 生活区、办公区的建设,进行施工现场的规划及布置,提前安排塔吊基础施工,进行钢 筋、混凝土、防水卷材、人防门等材料的采购。编写施工组织设计及主要施工方案,做 到技术先行。 2) 地下结构施工阶段(2015 年 03 月 26 日至 2016 年 1 月 15 日) 该阶段任务重,工期紧,春节前必须完成地下结构(地下三层),工作重点是:整 个地下结构施工将经历一个冬期,安排施工必须考虑对工程质量与进度的影响,重点解 决好冬施混凝土的保温、测温工作。 3) 地上主体结构施工阶段(2016 年 1 月至 2016 年 9 月) 该阶段是工程的关键阶段,期间要进行结构”长城杯”的检查验收,安全文明工地 的检查验收, 整个地上结构施工将经历一个雨期(2016 年), 安排施工应考虑雨期施工对 工程质量与进度的影响。 该施工阶段包括地上主体钢筋混凝土结构、 二次结构施工(2016 年 06 月) 。 为尽早插入初装修, 地上主体结构分三次验收, 即七层及以下进行第一次结构验收、 八层至十八层进行第二次结构验收,十九层以上进行第三次结构验收。在此阶段主要应 解决好钢筋安装、填充墙与主体结构的连接、预埋件的质量控制工作;对于屋面、建筑 外装修、室内装修、外饰线条或造型要提前进行深化设计,绘制施工节点大样图,经审 批后再进行施工,样板间的施工及验收等工作。 4) 装饰装修及设备安装施工阶段 装修与安装施工阶段不是一个独立的阶段,而是与主体结构施工阶段相互交叉的; 同时, 也只有这样, 才能保证总体进度计划按时完成。 该阶段包括所有室内装修以及水、 电、消防、通风、电梯等各专业施工,同时配合业主做好综合调试工作。装修工程在二
15
次结构施期间插入初装修施工,公共部分精装修工程随每层初装修完成跟进作业,机电 安装随装修进度穿插进行。 (1) 内装修施工:待结构分部位验收后,立即插入烟风道、内部隔墙施工,届时外 用电梯已提前进场安装到位;在门窗框安装后,基层抹灰湿作业采取墙面→地面→顶棚 的顺序进行施工;房间装修采取顶棚→墙面→地面的顺序进行施工。室内装修总的指导 思想先下后上;先样板,后大面;先屋面与楼层防水,后室内装修;先房间,后走道; 先湿作业,后干作业;先基层,后面层;完一间锁一间,完一层封一层,做好成品保护。 (2) 机电工程施工:水、电、通风等管道随土建配合施工,在塔吊拆除前完成各种 大型设备的吊装就位工作。 (3)自行车坡道施工:由于考虑住宅楼主体结构现场用地紧张,因此自行车坡道出 口待主体结构封顶,大部分周转材料退场后进行施工。 (4)屋面工程施工:屋面施工在结构封顶后适时进行;为了减小施工吊篮对屋面的 影响,将吊篮悬挂机构设置在 27 层结构内。 (5)外立面施工:住宅楼外立面装修内容包括基层处理和修补、外窗的安装以及外 墙涂料、外墙面砖的施工。结构验收后,从上向下进行外墙外保温、外墙面砖和外墙涂 料工程施工,可组成立体交叉作业。 5) 竣工调试清理验收阶段 该阶段主要组织好机电设备等系统调试与全负荷试车检测工作,安排成品保护人员 作好建筑产品的成品保护工作,配合建设单位组织好竣工验收工作。
3.3 施工组织机构及职能分工
3.3.1 组织机构设置 项目经理部由公司授权管理,以项目经理为核心全面实行项目法施工管理,有关生 产、技术、质量、经济、安全等各项工作实行项目经理责任制,对人、财、物进行独立 核算;建立岗位责任制,明确分工职责,落实岗位责任,各岗位各行其职。 项目部职能部门设为五部一室,即技术质量部、工程部、机电部、物资设备部、经 营部、综合办公室。
16
项目经理部组织机构见下图。
项目部组织机构图
技术质量部
经 营 部
机 电 部
物资设备部
综合办公室
张大伟
(技术主管) 杨亮、 高志远 (技术员) 辛生益
(质量主管) 刘克辉
(测量主管) 陈常波
(试验主管) 李文静
(资料主管)
赵彦斌
(机电经理)
陆京城
(水暖工长)
陈润祥
(电气工长)
王武生 (材料)
孙德仲
(材料主管)
任晓斌 (材料员)
吕炳林 (材料员)
刘学洋 (材料员)
李 明
(工程部长) 龚 林 (栋号长) 陈常波 (栋号长) 王春秋、 张淼
(安全员) 缪建平 (临 电)
阳星亮
(预算主管) 彭琳琳
(合同主管) 国 华
(预算员) 孙 睿
(预算员)
工 程 部
杨永其
(行政主任)
李培新
(消防保卫)
王海波
(劳务管理)
土建作业队 装修作业队 水电作业队
专 业 公 司 (分 包)
项 目 经 理 李福海(工程师)
项 目 总 工
刘建波(工程师)
生 产 副 经 理
杨 德 山(助 工)
3.3.2项目各岗位职责及分工
3.3.2.1项目经理职责
①代表企业实施项目管理,贯彻执行国家技术方针政策和强制性技术标准,执行企 业的科技管理制度。
②负责策划项目管理实施规划或施工组织设计,落实编制责任部门及人员。组织相 关部门对其进行会审,经项目经理审核签字后报企业技术负责人审批。
③完成项目承包责任书规定的任务。
④在授权范围内负责与业主、分包人及其他项目干系人的协调,解决项目实施中出 现的问题。
⑤生对项目实施全过程进行策划、组织、协调和控制,并在工程开工前负责向公司 汇报施工组织设计。
⑥组织分部工程地基验槽、基础、主体结构等验收及企业内部的竣工预验,参加建 设单位组织的竣工验收及工程保修工作。
3.3.2.2项目总工职责
①组织项目部专业技术人员进行图纸自审, 参加甲方代表组织的施工图纸会审和设 计交底并做好记录。
②主持项目经理部的技术质量管理工作及制定本项目技术质量管理细则。
③负责编写单位工程施工组织设计及冬、雨期施工技术措施,作好施工过程中的施 组变更、调整、中间检查记录,审批分部、分项工程施工方案。
④主持分项工程及地基验槽、基础、主体结构验收及企业内部的竣工预验,参加建 设单位组织的竣工验收。
⑤推广新技术、新工艺、新材料、新设备,努力提高施工工艺水平和操作技能。 ⑥负责组织每周一次的各专业技术协调会及质量分析会。
⑦组织各项技术资料的签证、收集、整理和归档,负责竣工档案编制及移交。 3.3.2.3生产副经理职责
①组织工程部门的相应人员编写施工组织设计中涉及施工管理的部分内容。 ②负责组织项目经理部日常的生产活动。
③协助项目经理完成质量职责,严格按施工组织设计(施工方案)组织施工,狠抓 过程管理,对过程工程质量负直接领导责任。
④对不符合质量标准的工艺、工序、检验批、分项、分部工程有权令其返工和停工
⑤审批混凝土开盘申请和鉴定。
⑥检查、指导和支持项目安全管理人员的工作,负责组织领导施工现场各类防护设 施、大型机械设备等投入使用前的验收工作,对重要的防护设施、重点施工部位的安全 性负直接领导责任。
⑦认真组织实施分部分项工程的安全技术交底, 对交底内容的落实情况实施跟踪管 理。
⑧组织领导本工程项目安全检查、对各类事故隐患的及时消除负直接领导责任。 3.3.2.4经营主管职责
①贯彻执行国家、地方有关法律、法规等,执行北方公司有关管理办法,全面负责 项目部经营管理工作,配合项目经理确保项目部经营管理目标的实现。
②负责工程预算、结算和工程索赔工作。
③负责制定合同履约及实施过程中出现重大设计变更或合同环境变更时的补充合 同(或协议)。
④负责审定项目部每月工程计划、报量、计量、支付及各种报表上报工作;负责组 织对公司的经营月报工作;工程竣工后负责组织编制经营管理工作总结。
⑤负责与业主、监理办理工程计量、支付、变更(索赔)等批复手续。
⑥负责材料、设备的认价工作。
⑦负责协助项目技术部门办理与业主的经济洽商。
⑧组织工程劳务、专业分包、材料、机械设备的招投标工作,审定分包方资质,参 与劳务、专业分包、材料供应商等施工队伍选择。
⑨负责合同管理工作,审定工程劳务、专业分包合同、材料、机械设备合同、补充 协议等。
3.3.2.5综合办公室主任职责
①全面负责施工现场的行政保卫工作,协助项目经理落实治保会职责,抓好保卫工 作方案的实施。根据工程进度情况,定期召开专职消防、护厂队会议,及时指导现场安 全保卫工作开展。
②负责所有参施人员、车辆证件的审核、发放和管理,搞好各种数字统计,建立保 卫工作档案和台帐。
③认真做好治安、消防、交通安全教育工作,采取入场教育、职工教育同外施人员 教育相结合的方法,注重教育效果,提高全体参施人员自我防范能力、遵章守纪的自觉
④指导各专业分承包单位做好各项规章制度的落实,定期组织保卫人员培训,不断 提高安全保卫人员的业务素质。
⑤参加施工组织设计中安全、保卫、消防方面的编审和生产例会,根据工程进度提 出保卫工作意见。
⑥同属地公安部门搞好合作,接受业主委员会和有关部门的监督、检查和指导,参 加与施工现场周边公安、消防、交通管理等部门,以及当地街道办事处、居(村)委会 的联系,协调处理好与当地居民发生的矛盾。
3.3.2.6项目专业技术负责人(技术员)职责
①认真熟悉图纸,进行图纸自审,问题汇总,参加甲方代表组织的施工图纸会审和 设计交底并做好记录。
②按公司项目管理体系文件要求,编制和贯彻施工组织设计、施工方案,并进行方 案和分项技术交底。参加危险和安全论证方案的编制。
③及时办理工程变更洽商、编制整理工程技术资料,组织材料检验和施工试验。 ④监督检查工程施工质量, 调整工序矛盾, 并及时解决施工中出现的一切技术问题。 ⑤负责编制分部、分项工程施工方案,并对专业工长、班组长进行技术交底,提出 保证质量、节约材料、安全施工等方面的技术组织措施和要求。
3.2.2.7项目安全主管(安全员)职责
①认真贯彻落实安全生产方针、政策、法律、法规和各项安全管理规范、标准,及 时传达贯彻上级有关安全生产的会议、文件和领导指示,并结合本公司实际,提出具体 贯彻落实的措施和办法。
②根据国家有关规定和公司发展的需要, 不断完善安全生产管理的各项规章制度和 各类安全操作规程,并监督执行。
③负责组织对本企业的安全生产检查工作, 落实 《安全生产一票否决制度考核办法》 和集团公司有关安全生产、文明施工的各项规章制度,对安全生产、文明施工负重要管 理责任。
④负责组织本企业开展安全生产月和《百日安全生产无事故竞赛》活动,以及文明 施工工地创建、环保达标工作;宣传安全生产法规,普及安全生产知识,不断提高公司 职工安全生产意识和素质。
⑤参加施工组织设计、施工方案的会审,参加施工现场临电、机械、各种脚手架等 项目的验收工作,并监督执行。
施队负责人进行安全生产培训、轮训,使上述人员做到持证上岗。
⑦负责职工因工伤亡事故的报告、调查、处理、统计分析工作,提出对事故有关责 任者的处理意见。
3.3.2.8质量主管(检查员)职责
①认真执行国家的施工规范、质量验收标准和公司的质量体系文件规定。
②全面负责工程的质量检查工作,对进货和过程质量进行跟踪监控,防止质量通病 的发生。
③施工过程中,严格执行“样板引路”、“三检”制度,认真做好验收记录。 ④发现进货和过程不合格或潜在不合格,严格按照《不合格品的控制工作程序》进 行处理,并及时验证处置结果,持有质量否决权。
⑤负责本项目(栋号)的质量总结、统计报表和质量台账(建立检验批、分项、分 部、单位工程的质量台帐,隐患通知书台帐,质量问题或事故台帐,工程质量的奖罚台 帐及其它各种台帐)。负责对钢筋、混凝土、砂浆强度台帐的检查,保证工程质量评定 的真实性、准确性、及时性。
⑥对本项目 (栋号) 范围内的检验批、 分项、 分部、 单位工程进行质量检查和评定, 参加隐、预检,基础及主体结构验收。纠正违章施工,必要时下达停工令,必须及时向 主管领导汇报。参加施工样板的签认工作。
⑦在项目总工主持下,按公司项目管理体系文件要求,编制质量计划,制定质量管 理措施,建立质量分析会制度,组织交底,并跟踪检查落实整改情况。
3.3.2.9项目专业工长职责
①熟悉掌握施工图纸,清楚了解本工种的施工工艺、操作规程,负责向班组进行施 工操作技术交底与安全技术交底。
②负责按施工技术标准,对分项工程的检验批质量进行验收,强化施工过程中的质 量控制与检验。
③负责进场建筑材料、设备检验;负责预拌混凝土联系工作及小票收集。
④组织分项工程的隐、预检工程验收。
⑤负责施工过程操作中的技术指导与检查,严把工序质量关。
⑥负责各工序样板施工及各专业的自检、专检和中间交接检验。
3.3.2.10项目测量员职责
①认真熟悉图纸,熟悉工程概况,结合技术交底、设计变更做好施工测量工作。
③负责楼层施工过程中的抄平、放线,做好原始记录,测量技术资料及时归档。 ④负责测量仪器的领送、保管、校准并建立台帐。
3.3.2.11项目试验员职责
①严格遵守试验操作规程, 认真填写试验记录, 对试验方法和提供的试验数据负责。 负责建立委托试验报告单的填写规范样表。
②对运至施工现场的原材料,按照取样规定采集样品,填写试验委托单送试验室进 行试验或复试,对采集样品的代表性负责。不得弄虚作假。
③在项目总工主持下,按公司项目管理体系文件要求,编制试验方案、试验计划及 见证取样计划。做好见证取样的协调工作,对试件的代表性和试验过程负责。
④定期按时取回试验报告,经自查无误后,及时移交资料管理员存档,并认真做好 试验台帐。
⑤负责建立现场标准养护室,现场试验室设备的购置及保养。
⑥负责混凝土小票收集、整理及混凝土坍落度的检查记录。塌落度检查结果,应记 录在混凝土小票上。现场检测混凝土,当质量出现异常时,应及时向上汇报,避免质量 问题的发生。
⑦负责大气测温,操作间、标养室测温。
⑧负责试块、试件的制作、养护、送检等工作。
3.3.2.12项目资料员职责
①在项目总工主持下,参加编制资料目标设计,制定总分包资料管理制度及措施, 并进行交底。
②建立收发文制度和规范、图集等受控文件借阅登记制度,对文件接收发放的及时 性、准确性负责,对文件的保存负责。
③负责收集、整理和保管各种质量记录、洽商、图纸、受控图集文件等资料,做到 整、齐、全、便。
④严格按照资料管理规程要求,对收集的资料进行把关,对不合格资料拒绝接收, 并跟踪落实整改情况,保证资料真实、及时、完整。
⑤负责建立资料移交签字制度和资料移交台帐,并对移交资料的完整负责。每周对 总分包资料进行检查,并填写资料检查记录(详见资料目标设计)。
⑥负责图纸、文件资料的编制、整理工作,保证一次交验合格。负责每周对总分包 电子版资料的收集,并保存完善。
参加工程质量会议和业务培训学习。
3.3.2.13项目材料员 (主管 ) 职责
①全面负责项目物资的管理工作,执行上级物资管理制度,制定工作计划和现场材 料管理及周转材料管理细则并组织实施,做到切实可行,责任明确。
②负责汇总编制单位工程物资采购计划、周转材料租赁计划、外委加工计划,合理 组织材料进场,抓好进场材料的数量和质量关。
③负责项目物资厂家考察、供方评定、招标采购、供应合同、结算、付款工作。 ④负责对进场材料的验收、保管、标识、发放、和材料核算的监管工作,参与成本 核算和经济活动分析。
⑤负责分包材料方法的制定并组织落实。材料定额及分部分项材料包干用量的核 准,指导材料用料工作。
⑥负抓好业务建设,使施工材料从计划订货、进场、消耗使用、统计核算、废旧物 资回收利用各个环节保持受控状态,抓好材料的有关台帐登记。
⑦负责物资(包括业主提供的物资)的质量验收、记录工作,保证不合格的物资不 投入工程使用,并将物资的质量证明、合格证等及时传递相关部门。
⑧负责现场材料管理及现场检查工作, 监督、 指导现场材料使用、 回收及码放工作。 3.3.2.14项目临电主管(管理员)职责
①负责编制本单位临电安全管理制度、奖罚规定、特殊时期的临电安全管理方案及 施工现场《临电施工方案》工作,经审核批准后,严格按照标准规定在现场严格组织实 施。
②负责组织本单位与各分包单位签订《临电使用安全协议书》工作;负责本单位施 工现场各分包单位的临电专业人员安全教育培训、考试、登记和签字工作;负责临电特 种作业人员有效证件审核和日常管理工作,并对有效证件审核结果负责。
③负责制定本单位的临电特种防护用品计划。 按照规定负责审核供货单位的营业执 照、资质、特种用品许可证及许可证,并对审核结果负责。严格按照标准规定,负责对 的临电设备用品实施计划、采购、鉴定、验收、使用、维修实施监督工作,并对过程控 制结果负责。
④负责本单位临电管理的资料归档工作,并保持其有效性。
⑤负责本单位施工区、生活区、办公区日常临电安全管理工作,按照规定组织专项 检查,并对存在的问题及时下发记录单和事故隐患通知单,做好问题或事故隐患反馈归
⑥对本单位施工区、生活区、办公区临电管理中,对违章指挥、违章作业人员有权 根据规定实施经济处罚,有权对危险作业场所实施停工处理,有权越级反映本单位临电 安全管理状况。
⑦负责组织本单位临电安全管理活动;负责对班组或临电专业维修人员实施《临电 安全技术交底》工作。
3.3.2.15项目专职(兼职)环保人员职责
①根据国家环境保护相关法律、法规及上级有关规定,负责制定本单位的环保规章 制度、奖罚办法,并监督实施,并根据规定对违规人员有经济处罚权。
②负责本单位对全员进行环境保护教育培训,并根据规定进行考试、登记工作。 ③负责本单位施工现场大气、扬尘、污水排放监督检查和监测工作,并根据各项指 标做好预控工作;防止环境污染事件发生。
④负责环境保护设施、设备的日常管理工作,做好保养、维修工作,确保环境保护 设施、设备有效使用。
⑤负责本单位环保手续的申办工作;负责本单位环境贯标工作。
⑥负责本单位环境保护工作内业资料的建立、收集、存档工作,确保内业资料齐全 有效。
⑦负责《施工组织设计》环保措施的落实工作,并参加专项环保措施审核,并根据 规定提出建议和修订工作。
3.3.2.16项目机械员
①认真贯彻落实安全生产方针、政策、法律、法规和各项安全管理规范、标准,在 安全主管领导下,做好机械设备备案和验收工作。
②按监督执法部门和公司管理体系文件要求,定期组织检查,排除隐患,建立项目 机械设备台帐、维修记录等管理资料,并妥善保存。
③参加机械设备选型,并提供相关技术参数。
④建立机械设备使用安全操作规程。
3.3.2.16项目消防管理员
①积极贯彻“预防为主、防消结合、综合治理”的方针,加强领导,认真落实国家 颁发的法律、法规以及企业的有关防火规章。
②定期组织全体人员进行有关法律、条例规章的宣传,抓好落实工作,发现隐患提 出整改意见,对违章行为及时制止和处理。
④参加消防事故防范措施的制定,对义务消防进行防火指导,负责用火管理和防火 器材的管理及检查工作。负责消防资料的整理、归档工作。
3.4 主要项目工程量表
3.5施工进度计划
3.5.1施工总工期
本工程计划开工日期为 2015年 3月 1日,竣工日期拟定为 2017年 1月 27日,施 工计划工期为 698日历天。
3.5.2主要节点工期计划
准备工作 2015年 03月 1日至 04月 15日
基础工程 2015年 03月 26日至 2016年 1月 15日
地上结构 2016年 1月至 2016年 9月
结构封顶 2016年 09月 07日
砌体工程 2016年 06月 03日 -2016年 09月 06日
内装修工程 2016年 07月 22日 -2016年 9月 18日
外装修工程 2016年 10月 30日 -2016年 12月 18日
机电工程 2016年 12月 17日调试完毕
竣工验收 2017年 1月 27日
3.5.3详细施工进度计划见附表施工进度计划横道图。
3.6原材料、构配件、设备的加工及采购计划
3.6.1施工周转材料进场计划
根据施工进度计划,按工程段号需要,每个段号配备一个流水段梁、柱、板所用材 料。各种周转材料需用量计划见下表。
3.6.2主要施工机械计划用表
3.7主要劳动力计划
3.7.1 项目部人员配置
根据工程特点,按照总承包管理组织机构设置的要求确定主要管理人员岗位,遵循 合理分工,密切协作,因事设职和因职选人的原则,建立具有丰富施工经验,有开拓精 神和工作效率高的项目部。
3.7.2 劳动队伍选择与组织
招标选择精干的施工队伍。根据采用的施工组织方式,确定合理的劳动力组织,建 立相应的专业和混合施工班组。对施工队人员进行技术等级复核,并对操作人员进行技 能抽验。特殊工种必须持有相应的技术等级证书上岗操作。
施工主要劳动力计划表
劳动力曲线图如下:
3.8协调与配合
3.8.1总包合同范围
3.8.2总包单位组织内部专业分包单位的施工项目
3.8.3总包单位组织外部分包单位的施工项目
3.8.4设备、构件、配件、加工品、材料采购的分工
3.8.5组织协调方式
3.8.5.1内部协调
①项目部每周五召开安全、生产例会,每周二召开质量例会,每月 25日召开成本 分析会并于每三层施工完毕时召开一次技术总结会及与专业单位协调会。 通过以上措施 保证工程的工期、质量、安全、降低成本的目标,协调、管理好参加工程管理和施工的 各方。
②项目部根据施工合同制定年度、月度及周进度计划,并传达给各分包单位,每周 五下午 4:00组织各分包单位碰头会, 总结当日及前一段时期进度、 质量等方面情况, 并 提出次日及下一步进度、质量要求。
3.8.5.2与业主方的协调与配合措施
①定期参与业主例会,讨论解决施工过程中出现的各种矛盾及问题,理顺每一阶段 的关系,使整个施工过程井然有序。
②根据总体进度计划安排,对分包商的考察时间、进退场时间作出部署,制定分包 商的招投标计划、进场计划。业主需要时,协助业主编制招标文件、考察队伍,精心选
择施工质量好、信誉高的分包商,以确保满足施工需要。
③利用我公司的丰富施工经验和全面配套的专业综合能力,指导和协助弱电、设备 等分包作好专业图纸深化设计,审核弱电分包的深化设计及施工方案,把好技术关、质 量关。
④对业主提供的材料设备提前编制进场计划,必要时协助业主进行考察、订货,确 保工程需要。利用我公司完善的信息系统及供应网络,选择诚信度高、质量好的供应商 推荐给业主,供业主决策参考。同时,在材料、设备的技术指标和功能参数等方面为业 主提供技术支持。
⑤根据施工进度需要,编制图纸需求计划,提前与业主、监理工程师、设计人进行 沟通,提前确定设计图纸。认真熟悉图纸、洽商管理,减少变更,从而达到降低造价、 控制投资的目的。
⑥对于专业分包商和供应商, 在施工的各阶段将按照业主的要求进行科学管理以及 给予必要的支持。
⑦积极协助业主处理一些力所能及的工作,如处理和协调好与相关部门的关系等。 ⑧对于业主另行分包的工程,我公司将积极与业主沟通,提前移交工作面,为施工 创造条件,确保综合系统调试的按期完成,使本工程竣工后即可达到使用条件。
⑨配合业主完成总平面的管理协调工作,将对室外工程的影响降到最低。
3.8.5.3与监理单位的协调与配合措施
①技术部、 质量部、 安全部安排专人对口监理各专业工程师, 与监理单位紧密合作, 在施工全过程中,严格按照经业主、监理批准的《施工组织设计》进行全面管理,以严 格的施工管理程序,达到工程所要求的各项技术、质量、经济指标。
②施工过程中所有的施工方案均要在施工前规定的时间内报送监理等相关单位。 ③编制月计划、季度及年度进度计划,同时编写主要工程材料、设备的采购及进场 等计划安排,让监理有总体的控制。
④向监理阐明项目建立的质量管理体系、技术管理体系和质量保证体系,以便很好 的控制工程质量。
⑤当工程达到基本交验条件时, 向监理工程师汇报全面的质量情况和使用功能并进 行全面检查。
⑥按时参加监理工程师组织与主持的每周二下午 14:00监理例会。监理例会是履 约各方沟通情况、交流信息、协调处理、研究解决合同履行中存在的各方面问题的主要 协调方式。
⑦按照监理等相关单位的合理意见进行修改和完善后方可用来指导现场施工。 现场 的所有人员的资料均要在规定时间内报送监理等相关单位以便于管理, 若有改动将及时 报批后才能进行。用于施工的各种材料设备进出均要在规定时间向监理等相关单位报 批。
⑧施工过程中在班组“自检”和项目经理部“专检”的基础上,虚心接受和服从监 理的检查和验收,服从监理的“四控” (质量控制、安全控制、工期控制和造价控制)、 “两管”(合同管理和资料管理)、监督和协调,并按照监理工程师提出的要求,予以 改正,以便监理工作顺利进行。
3.8.5.4与分包方配合
?我公司将严格履行总承包责任、权力和义务,为各分包单位(包括自行分包单位 及业主另行分包单位)提供优质、高效的服务,保证关键工序和关键线路。主要措施如 下:
①提供现场已有的脚手架、操作平台,以及为满足分包单位使用要求的特殊脚手架 (包括配套的安全设施);
②提供现场的垂直运输机械设备并分配好使用时间;
③合理分配和提供现场堆场、道路,及时提供足够的和无障碍的工作面;
④提供现场办公场地及库房等临时设施;
⑤在施工现场提供公共部分的照明及工作面附近的临时电源;
⑥在施工现场靠近工作面处提供临时水源接口;
⑦提供现场警卫、公共部位消防设施;
⑧提供外架安全防护和公共通道安全防护;
⑨提供现场轴线、高程等相关测量资料以及楼层测点;
⑩提供有关文件要求的其他措施。
?在总承包全面对业主负责的基础上,与各分包单位通过合同及协议明确双方责 任,并以此作为施工总承包协调管理的依据。对分包单位实行严格管理,充分协调各专 业分包相互之间的关系。 总包方根据总的施工进度计划制定分包施工队的进场时间和相 应的材料进场时间。
?分包施工队进场以前要签定承包合同,合同中要明确本工程要达到的质量、文明 安全、工期、环保的工程指标,各分包施工队要签定工程质量保证书、文明安全施工保 证书、工期保证书、环保保证书。
?各施工队在进场之前要向总包方交纳一定数量的工程质量、文明安全施工、施工
工期、环境保护保证金。
?分包方与总包方的密切配合是完成本工程各项指标的重点, 因此总包方将在招标 阶段对分包方的资质和业绩进行审核; 各分包方在进场时要配备素质较高的管理人员和 施工队参与工程建设,对此总包方同样要予以准确的核实。对于分包方配备的管理人员 和施工队的素质要求在合同文本中要明确的体现。
?以总体工期网络计划为基准,合理安排各分包单位的施工流水节拍,及时进行工 序穿插;选派相应的专业技术管理人员解决各专业分包单位存在的技术、进度、质量问 题; 通过召开协调会解决施工过程中所出现的总承包与分包之间及分包与分包之间的各 种矛盾,以使整个工程能顺利施工,达到相应的各项指标,对于机电安装与其他专业分 包的配合是分包配合的重点。
第四章 施工准备
4.1 技术准备
4.1.1一般性准备工作
4.1.1.1图纸会审
组织工程管理人员熟悉图纸,了解设计意图,查找图纸问题并汇总,确定设计交底 时间,作好图纸会审记录,并进行交底。
4.1.1.2技术文件准备
准备好本工程所需的规范、规程、图集和法规。
4.1.1.3组织培训
组织有关人员结合设计图纸,学习规范、规程等强制性条文内容,加深对规范的理 解和掌握。
4.1.2计量、测量、试验器具配置计划
根据本工程特点和质量要求,选配计量、试验等器具,确保精度满足规范、标准要 求,具体配置详见下表:
计量、测量、试验器具配置表
4.1.3技术工作计划
4.1.3.1施工方案编制计划
施工方案编制计划
37
38
4.1.3.2试验、检测计划
①在现场设立 15㎡标准养护室,内设自动恒温恒湿装置,控制温度
(20±2℃)和湿度≥ 95%达到标准养护条件,配备试模、振动台等试验器具。 ②按京建质(2009) 289号文要求《北京市建设工程见证取样和送检管理规定(试 行)》的通知要求对应用于本工程涉及结构安全的试块、试件和材料必须 100%实行见 证取样和送检。
③具体详见《朝阳区来广营乡清河营村住宅及配套、商业金融(4号地)项目试验 方案》
④试验计划
39
4.1.1.1样板施工计划
施工过程中对主要的分项工程实施样板引路制度,施工前编制样板施工计划,经监 理人审批后施工,施工过程及施工成品满足质量验收标准。样板施工完成后报监理人确 认后进行大面积施工。样板施工计划详见下表
40
样板施工计划
41
4.1.4 危险性较大工程安全专项施工方案专家评审计划
4.1.5 新技术推广应用计划
42
4.1.6高程引测与建筑物定位
4.1.6.1在工程开工前,及时和业主进行现场原始永久性的基准标桩的交接,交桩成 果为三维坐标,与施工设计图纸坐标系相同,桩点为本工程的定位依据点。交接桩测量 资料必须齐全,并应附有标桩示意图,标明各种标桩平面位置和标高,并附文字说明, 依照资料,现场核对进行点交并签字。
4.1.6.2经检查控制点无误后利用经纬仪将控制点投测到作业面上, 然后将经纬仪移 至作业面检查投测点无误后再进行细部放样;控制点的投测和细部放样过程中应遵循 “先整体、后局部,先控制、后细部,步步有校核”的原则,根据现场条件,高程控制 点建立在永久建筑物上,至少建立三个高程控制点,便于以后复核检查。
详见《朝阳区来广营乡住宅及配套、商业金融(4号地)项目测量施工方案》
43
44
4.2 生产准备
4.2.1施工现场总平面布置原则
根据施工现场实际情况,对现场进行统筹安排,布局合理。施工现场布置既要满足 施工生产需要,为施工生产提供便利条件,同时在基础施工阶段对施工现场平面布置时 考虑下一步主体结构施工阶段及装修施工阶段的布局,避免现场二次规划过多改变。
4.2.2施工水源、电源引入及准备计划 4.2.1.1用水量计算 (1)施工生产用水量 q1
其中:
k1—未预计的施工用水系数,取 1.1 Q1—每班计划完成工程量 N1—施工用水定额
K2—现场施工用水不均衡系数,取 1.5
结构施工期间主要施工用水项目及用水量见下表:
K N Q k q 05. 7360085. 1000
1. 13600821111=??? ?????=?∑
=
(2)机械用水量 q2
3600
83
2
212?∑=K N Q k q
其中:
k1—未预计的施工用水系数,取 1.1 Q2—同一种机械台数 N2—施工机械用水定额 主要施工机械及用水量见下表 :
360082
1111?∑
=K N Q k q
45
K N Q k q 01. 0360080. 21851. 13600832212=??
?
?????=?∑
=
(3)现场生活用水量 q3 3600
84
313??=
t K N P q
其中:
P1—施工现场高峰昼夜人数,取 600人 N3—施工现场生活用水定额 40L/人 K3—施工现场生活用水不均衡系数 取 1.5 t —每天工作班数 1 现场生活用水量
t K N P q 25. 13600
815. 140600360083
313=????=??=
(4)生活区生活用水量 q4
3600
244
424?=K N P q
注:生活区设置在现场外,不予考虑,取 0 L/S。 (5)消防用水量 q5
本工程施工场地面积小于 25ha ,取 q5 =10L/S (6)总用水量 Q
因为 q1 +q2 +q3 +q4 20 0.55
调整信息 ........................................
梁刚度放大系数是否按 2010规范取值:是
托墙梁刚度增大系数:BK_TQL = 1.00 梁端弯矩调幅系数:BT = 0.85 梁活荷载内力增大系数:BM = 1.00 连梁刚度折减系数:BLZ = 1.00 梁扭矩折减系数:TB = 0.40 全楼地震力放大系数:RSF = 1.00 0.2Vo 调整分段数:VSEG = 0 0.2Vo 调整上限:KQ_L = 2.00 框支柱调整上限:KZZ_L = 5.00 顶塔楼内力放大起算层号:NTL = 0 顶塔楼内力放大:RTL = 1.00 框支剪力墙结构底部加强区剪力墙抗震等级自动提高一级 :是
柱实配钢筋超配系数 CPCOEF91 = 1.15
墙实配钢筋超配系数 CPCOEF91_W = 1.15
是否按抗震规范 5.2.5调整楼层地震力 IAUTO525 = 1
弱轴方向的动位移比例因子 XI1 = 0.00
强轴方向的动位移比例因子 XI2 = 0.00
是否调整与框支柱相连的梁内力 IREGU_KZZB = 0
薄弱层判断方式:按高规和抗规从严判断
强制指定的薄弱层个数 NWEAK = 0
薄弱层地震内力放大系数 WEAKCOEF = 1.25
强制指定的加强层个数 NSTREN = 0
配筋信息 ........................................
梁箍筋强度 (N/mm2): JB = 270
柱箍筋强度 (N/mm2): JC = 270
墙水平分布筋强度 (N/mm2): FYH = 210
墙竖向分布筋强度 (N/mm2): FYW = 300
边缘构件箍筋强度 (N/mm2): JWB = 210
梁箍筋最大间距 (mm): SB = 100.00
柱箍筋最大间距 (mm): SC = 100.00
墙水平分布筋最大间距 (mm): SWH = 200.00
墙竖向分布筋配筋率 (%): RWV = 0.30
结构底部单独指定墙竖向分布筋配筋率的层数 : NSW = 0
结构底部 NSW 层的墙竖向分布配筋率 (%): RWV1 = 0.60
梁抗剪配筋采用交叉斜筋时
箍筋与对角斜筋的配筋强度比 : RGX = 1.00
设计信息 ........................................
结构重要性系数 : RWO = 1.00
钢柱计算长度计算原则 (X向 /Y向 ): 有侧移 /有侧移
梁端在梁柱重叠部分简化 : 不作为刚域
柱端在梁柱重叠部分简化 : 不作为刚域
是否考虑 P-Delt 效应:否
柱配筋计算原则 : 按双偏压计算
按高规或高钢规进行构件设计 : 否
钢构件截面净毛面积比 : RN = 0.85
梁保护层厚度 (mm): BCB = 20.00
柱保护层厚度 (mm): ACA = 20.00
剪力墙构造边缘构件的设计执行高规 7.2.16-4: 是
框架梁端配筋考虑受压钢筋 : 是
结构中的框架部分轴压比限值按纯框架结构的规定采用 :否
当边缘构件轴压比小于抗规 6.4.5条规定的限值时一律设置构造边缘构件 : 是 是否按混凝土规范 B.0.4考虑柱二阶效应 : 否
支撑按柱设计临界角度 : 20.00
荷载组合信息 ........................................
恒载分项系数 : CDEAD= 1.20
活载分项系数 : CLIVE= 1.40
风荷载分项系数 : CWIND= 1.40
水平地震力分项系数 : CEA_H= 1.30
竖向地震力分项系数 : CEA_V= 0.50
温度荷载分项系数 : CTEMP = 1.40
吊车荷载分项系数 : CCRAN = 1.40
特殊风荷载分项系数 : CSPW = 1.40
活荷载的组合值系数 : CD_L = 0.70
风荷载的组合值系数 : CD_W = 0.60
重力荷载代表值效应的活荷组合值系数 : CEA_L = 0.50
重力荷载代表值效应的吊车荷载组合值系数 :CEA_C = 0.50
吊车荷载组合值系数 : CD_C = 0.70
温度作用的组合值系数 :
仅考虑恒载、活载参与组合 : CD_TDL = 0.60
考虑风荷载参与组合 : CD_TW = 0.00
考虑地震作用参与组合 : CD_TE = 0.00
砼构件温度效应折减系数 : CC_T = 0.30
剪力墙底部加强区的层和塔信息 .......................
层号 塔号
1 1
用户指定薄弱层的层和塔信息 .........................
层号 塔号
用户指定加强层的层和塔信息 .........................
层号 塔号
约束边缘构件与过渡层的层和塔信息 ...................
层号 塔号 类别
1 1 约束边缘构件层
2 1 约束边缘构件层
*********************************************************
* 各层的质量、质心坐标信息 *
*********************************************************
层号 塔号 质心 X 质心 Y 质心 Z 恒载质量 活载质量 附加质量 质量比
(m) (m) (t) (t)
9 1 68.615 9.059 23.690 522.5 52.0
0.0 0.92
8 1 68.614 9.106 22.090 569.9 52.0 0.0 1.03
7 1 68.614 9.087 18.410 549.9 52.0 0.0 1.00
6 1 68.614 9.087 15.610 549.9 52.0 0.0 1.00
5 1 68.614 9.087 12.810 549.9 52.0 0.0 0.74
4 1 69.221 7.338 10.010 752.0 57.2 0.0 0.75
3 1 72.022 10.471 7.210 1001.8 82.3 0.0 5.33(>1.5不满足高规 3.5.6条 )
2 1 65.917 12.280 3.690 191.2 12.1 0.0 0.36
1 1 72.729 11.147 2.000 550.8 6.4 0.0 1.00
活载产生的总质量 (t): 417.945
恒载产生的总质量 (t): 5237.808
附加总质量 (t): 0.000
结构的总质量 (t): 5655.753
恒载产生的总质量包括结构自重和外加恒载
结构的总质量包括恒载产生的质量和活载产生的质量和附加质量
活载产生的总质量和结构的总质量是活载折减后的结果 (1t = 1000kg)
*********************************************************
* 各层构件数量、构件材料和层高 *
*********************************************************
层号 (标准层号 ) 塔号 梁元数 柱元数 墙元数 层高 累计高度
(混凝土 /主筋 ) (混凝土 /主筋 ) (混凝土 /主筋 ) (m) (m)
1( 1) 1 168(25/ 360) 79(25/ 360) 0(30/ 300) 2.000
2.000
2( 2) 1 53(25/ 360) 79(25/ 360) 0(30/ 300) 1.690
3.690
3( 3) 1 249(25/ 360) 79(25/ 360) 0(30/ 360) 3.520 7.210
4( 4) 1 202(25/ 360) 67(25/ 360) 0(30/ 360) 2.800 10.010
5( 5) 1 169(25/ 360) 59(25/ 360) 0(30/ 360) 2.800 12.810
6( 6) 1 169(25/ 360) 59(25/ 360) 0(30/ 360) 2.800 15.610
7( 7) 1 169(25/ 360) 59(25/ 360) 0(30/ 360) 2.800 18.410
8( 7) 1 169(25/ 360) 59(25/ 360) 0(30/ 360) 3.680 22.090
9( 7) 1 169(25/ 360) 59(25/ 360) 0(30/ 360) 1.600 23.690
*********************************************************
* 风荷载信息 *
*********************************************************
层号 塔号 风荷载 X 剪力 X 倾覆弯矩 X 风荷载 Y 剪力 Y 倾覆 弯矩 Y
9 1 19.19 19.2 30.7 66.58 66.6 106.5 8 1 42.35 61.5 257.2 147.09 213.7 892.8 7 1 29.15 90.7 511.1 101.52 315.2 1775.4 6 1 26.81 117.5 840.1 93.59 408.8 2919.9 5 1 24.41 141.9 7.5 85.41 494.2 4303.7 4 1 27.59 169.5 1712.1 79.47 573.7 5910.0 3 1 64.51 234.0 2535.8 97.56 671.2 8272.7 2 1 28.36 262.4 2979.2 43.07 714.3 9479.8 1 1 31.89 294.3 3567.8 48.49 762.8 11005.4
====================================================================== =====
各楼层等效尺寸 (单位 :m,m**2)
====================================================================== =====
层号 塔号 面积 形心 X 形心 Y 等效宽 B 等效高 H 最大宽 BMAX 最小宽 BMIN
1 1 919.06 72.57 10.44 48.50 27.42 50.29
24.00
2 1 120.90 64.72 12.98 37.33 3.90 37.33
3.90
3 1 919.06 72.57 10.44 48.50 27.42 50.29 24.00
4 1 697.81 69.12 6.84 46.04 15.46 46.05
15.45
5 1 499.26 68.60 8.77 44.87 11.64 44.87 11.64
6 1 499.26 68.60 8.77 44.87 11.64 44.87 11.64
7 1 499.26 68.60 8.77 44.87 11.64 44.87 11.64
8 1 499.26 68.60 8.77 44.87 11.64 44.87 11.64
9 1 499.26 68.60 8.77 44.87 11.64 44.87 11.64
====================================================================== =====
计算信息
====================================================================== =====
计算日期 : 2015. 3.26
开始时间 : 14:18:58
可用内存 : 1257.0MB
第一步 : 数据预处理
第二步 : 计算每层刚度中心、自由度、质量等信息
第三步 : 组装刚度矩阵并分解
第四步 : 形成荷载向量
第五步 : 计算位移
第六步 : 计算杆件内力
结束日期 : 2015. 3.26
时间 : 14:19:22
总用时 : 0: 0:24
====================================================================== =====
各层刚心、偏心率、相邻层侧移刚度比等计算信息
Floor No : 层号
Tower No : 塔号
Xstif , Ystif : 刚心的 X , Y 坐标值
Alf : 层刚性主轴的方向
Xmass , Ymass : 质心的 X , Y 坐标值
Gmass : 总质量
Eex , Eey : X, Y 方向的偏心率
Ratx , Raty : X, Y 方向本层塔侧移刚度与下一层相应塔侧移刚度的比值 (剪切刚度 ) Ratx1, Raty1 : X, Y 方向本层塔侧移刚度与上一层相应塔侧移刚度 70%的比值 或上三层平均侧移刚度 80%的比值中之较小者
RJX1, RJY1, RJZ1: 结构总体坐标系中塔的侧移刚度和扭转刚度 (剪切刚度 )
RJX3, RJY3, RJZ3: 结构总体坐标系中塔的侧移刚度和扭转刚度 (地震剪力与地震层间位 移的比 )
====================================================================== =====
Floor No. 1 Tower No. 1
Xstif= 70.2275(m) Ystif= 10.7770(m) Alf = 0.0863(Degree)
Xmass= 72.7293(m) Ymass= 11.1469(m) Gmass(活 荷 折 减 )= 563.6763( 557.2398)(t)
Eex = 0.1538 Eey = 0.0259
Ratx = 1.0000 Raty = 1.0000
薄弱层地震剪力放大系数 = 1.00
RJX1 = 5.7838E+06(kN/m) RJY1 = 7.4816E+06(kN/m) RJZ1 = 0.0000E+00(kN/m) ---------------------------------------------------------------------------
Floor No. 2 Tower No. 1
Xstif= 70.2377(m) Ystif= 10.7743(m) Alf = 0.0807(Degree)
Xmass= 65.9167(m) Ymass= 12.2800(m) Gmass(活 荷 折 减 )= 215.3624( 203.2657)(t)
Eex = 0.2718 Eey = 0.1077
Ratx = 1.6574 Raty = 1.6574
薄弱层地震剪力放大系数 = 1.00
RJX1 = 9.5862E+06(kN/m) RJY1 = 1.2400E+07(kN/m) RJZ1 = 0.0000E+00(kN/m) ---------------------------------------------------------------------------
Floor No. 3 Tower No. 1
Xstif= 70.2079(m) Ystif= 10.7829(m) Alf = 0.0972(Degree)
Xmass= 72.0221(m) Ymass= 10.4710(m) Gmass(活 荷 折 减 )= 1166.4742( 1084.1523)(t)
Eex = 0.1069 Eey = 0.0209
Ratx = 0.1107 Raty = 0.1107
薄弱层地震剪力放大系数 = 1.00
RJX1 = 1.0609E+06(kN/m) RJY1 = 1.3723E+06(kN/m) RJZ1 = 0.0000E+00(kN/m) ---------------------------------------------------------------------------
Floor No. 4 Tower No. 1
Xstif= 68.9628(m) Ystif= 8.8631(m) Alf = 0.0000(Degree)
Xmass= 69.2208(m) Ymass= 7.3384(m) Gmass(活 荷 折 减 )=
866.3782( 809.1725)(t)
Eex = 0.0163 Eey = 0.1099
Ratx = 1.7241 Raty = 1.7370
薄弱层地震剪力放大系数 = 1.00
RJX1 = 1.8291E+06(kN/m) RJY1 = 2.3838E+06(kN/m) RJZ1 = 0.0000E+00(kN/m) ---------------------------------------------------------------------------
Floor No. 5 Tower No. 1
Xstif= 68.6000(m) Ystif= 9.4334(m) Alf = 0.0000(Degree)
Xmass= 68.6143(m) Ymass= 9.0874(m) Gmass(活 荷 折 减 )= 653.8218( 601.8446)(t)
Eex = 0.0010 Eey = 0.0259
Ratx = 0.9204 Raty = 0.8826
薄弱层地震剪力放大系数 = 1.00
RJX1 = 1.6836E+06(kN/m) RJY1 = 2.1040E+06(kN/m) RJZ1 = 0.0000E+00(kN/m) ---------------------------------------------------------------------------
Floor No. 6 Tower No. 1
Xstif= 68.6000(m) Ystif= 9.4334(m) Alf = 0.0000(Degree)
Xmass= 68.6143(m) Ymass= 9.0873(m) Gmass(活 荷 折 减 )= 653.8197( 601.8428)(t)
Eex = 0.0010 Eey = 0.0259
Ratx = 1.0000 Raty = 1.0000
薄弱层地震剪力放大系数 = 1.00
RJX1 = 1.6836E+06(kN/m) RJY1 = 2.1040E+06(kN/m) RJZ1 = 0.0000E+00(kN/m) ---------------------------------------------------------------------------
Floor No. 7 Tower No. 1
Xstif= 68.6000(m) Ystif= 9.4334(m) Alf = 0.0000(Degree)
Xmass= 68.6143(m) Ymass= 9.0873(m) Gmass(活 荷 折 减 )= 653.8198( 601.8429)(t)
Eex = 0.0010 Eey = 0.0259
Ratx = 1.0000 Raty = 1.0000
薄弱层地震剪力放大系数 = 1.00
RJX1 = 1.6836E+06(kN/m) RJY1 = 2.1040E+06(kN/m) RJZ1 = 0.0000E+00(kN/m) ---------------------------------------------------------------------------
Floor No. 8 Tower No. 1
Xstif= 68.6000(m) Ystif= 9.4495(m) Alf = 0.0000(Degree)
Xmass= 68.6138(m) Ymass= 9.1064(m) Gmass(活 荷 折 减 )= 673.8763( 621.8995)(t)
Eex = 0.0009 Eey = 0.0253
Ratx = 0.4405 Raty = 0.4405
薄弱层地震剪力放大系数 = 1.00
RJX1 = 7.4160E+05(kN/m) RJY1 = 9.2680E+05(kN/m) RJZ1 = 0.0000E+00(kN/m) ---------------------------------------------------------------------------
Floor No. 9 Tower No. 1
Xstif= 68.6000(m) Ystif= 9.3943(m) Alf = 0.0000(Degree)
Xmass= 68.6149(m) Ymass= 9.0592(m) Gmass(活 荷 折 减 )= 626.4699( 574.4930)(t)
Eex = 0.0011 Eey = 0.0267
Ratx = 12.1670 Raty = 12.1670
薄弱层地震剪力放大系数 = 1.00
RJX1 = 9.0230E+06(kN/m) RJY1 = 1.1276E+07(kN/m) RJZ1 = 0.0000E+00(kN/m) ---------------------------------------------------------------------------
X 方向最小刚度比 : 1.0000(第 1层第 1塔 )
Y 方向最小刚度比 : 1.0000(第 1层第 1塔 )
====================================================================== ======
结构整体抗倾覆验算结果
====================================================================== ======
抗倾覆力矩 Mr 倾覆力矩 Mov 比值 Mr/Mov 零应力区 (%)
X 风荷载 1406814.5 4647.5 302.70 0.00
Y 风荷载 921268.6 12046.9 76.47 0.00
X 地 震 1366424.4 0.0 13664244.00 0.00
Y 地 震 894818.8 0.0 8948187.00 0.00
====================================================================== ======
结构舒适性验算结果 (仅当满足规范适用条件时结果有效 )
====================================================================== ======
按高钢规计算 X 向顺风向顶点最大加速度 (m/s2) = 0.024
按高钢规计算 X 向横风向顶点最大加速度 (m/s2) = 0.003
按荷载规范计算 X 向顺风向顶点最大加速度 (m/s2) = 0.025
按荷载规范计算 X 向横风向顶点最大加速度 (m/s2) = 0.004
按高钢规计算 Y 向顺风向顶点最大加速度 (m/s2) = 0.056
按高钢规计算 Y 向横风向顶点最大加速度 (m/s2) = 0.003
按荷载规范计算 Y 向顺风向顶点最大加速度 (m/s2) = 0.054
按荷载规范计算 Y 向横风向顶点最大加速度 (m/s2) = 0.023
///////////////////////////////////////////////////////////////////////////
|公司名称 : | | | | SATWE 位移输出文件 | | 文件 名称 : WDISP.OUT | | |
| 工程名称 : 设计人 : | | 工程代号 : 校核人 : 日期 :2015/ 3/26 |
///////////////////////////////////////////////////////////////////////////
所有位移的单位为毫米
Floor : 层号
Tower : 塔号
Jmax : 最大位移对应的节点号
JmaxD : 最大层间位移对应的节点号
Max-(Z) : 节点的最大竖向位移
h : 层高
Max-(X), Max-(Y) : X,Y方向的节点最大位移
Ave-(X), Ave-(Y) : X,Y方向的层平均位移
Max-Dx , Max-Dy : X,Y方向的最大层间位移
Ave-Dx , Ave-Dy : X,Y方向的平均层间位移
Ratio-(X),Ratio-(Y): 最大位移与层平均位移的比值
Ratio-Dx,Ratio-Dy : 最大层间位移与平均层间位移的比值
Max-Dx/h, Max-Dy/h : X,Y方向的最大层间位移角
DxR/Dx,DyR/Dy : X,Y方向的有害位移角占总位移角的百分比例
Ratio_AX,Ratio_AY : 本层位移角与上层位移角的 1.3倍及上三层平均位移角的 1.2倍的 比值的大者
X-Disp , Y-Disp , Z-Disp:节点 X,Y ,Z 方向的位移
=== 工况 1 === X 方向风荷载作用下的楼层最大位移
Floor Tower Jmax Max-(X) Ave-(X) Ratio-(X) h
JmaxD Max-Dx Ave-Dx Ratio-Dx Max-Dx/h DxR/Dx Ratio_AX
9 1 1031 2.15 2.10 1.02 1600.
1031 0.02 0.02 1.01 1/9999. 99.9% 1.00
8 1 917 2.12 2.08 1.02 3680.
917 0.19 0.18 1.02 1/9999. 12.7% 2.51
7 1 803 1.94 1.89 1.02 2800.
913 0.16 0.16 1.03 1/9999. 22.0% 1.44
6 1 689 1.78 1.74 1.02 2800.
689 0.20 0.19 1.03 1/9999. 18.4% 1.41
5 1 575 1.58 1.55 1.02 2800.
575 0.23 0.23 1.02 1/9999. 35.5% 1.16
4 1 444 1.37 1.33 1.03 2800.
446 0.33 0.31 1.07 1/8498. 81.8% 1.33
3 1 276 1.06 0.99 1.07 3520.
288 0.76 0.69 1.11 1/4613. 51.5%
1.93
2 1 271 0.38 0.32 1.19 1690.
267 0.27 0.19 1.44 1/6242. 42.0% 0.64
1 1 90 0.14 0.11 1.27 2000.
90 0.14 0.11 1.27 1/9999. 98.0% 0.41
X 方向最大层间位移角 : 1/4613.(第 3层第 1塔 )
X 方向最大位移与层平均位移的比值 : 1.27(第 1层第 1塔 )
X 方向最大层间位移与平均层间位移的比值 : 1.44(第 2层第 1塔 )
=== 工况 2 === Y 方向风荷载作用下的楼层最大位移
Floor Tower Jmax Max-(Y) Ave-(Y) Ratio-(Y) h
JmaxD Max-Dy Ave-Dy Ratio-Dy Max-Dy/h DyR/Dy Ratio_AY
9 1 1031 6.02 5.92 1.02 1600.
1032 0.11 0.11 1.01 1/9999. 99.9% 1.00
8 1 917 5.91 5.81 1.02 3680.
918 0.66 0.66 1.00 1/5579. 20.2% 2.02
7 1 803 5.25 5.16 1.02 2800.
804 0.60 0.60 1.00 1/4641. 21.2% 1.45
6 1 689 4.64 4.55 1.02 2800.
689 0.73 0.73 1.01 1/3824. 10.3% 1.41
5 1 575 3.91 3.83 1.02 2800.
576 0.82 0.80 1.02 1/3411. 0.5% 1.10
4 1 444 3.09 3.02 1.02 2800.
446 0.85 0.80 1.06 1/3303. 49.6% 0.94
3 1 276 2.24 2.22 1.01 3520.
310 1.58 1.50 1.05 1/2224. 39.0%
1.28
2 1 249 0.89 0.77 1.16 1690.
267 0.62 0.50 1.23 1/2735. 48.9% 0.65
1 1 152 0.28 0.24 1.20 2000.
152 0.28 0.24 1.20 1/7082. 97.5% 0.34
Y 方向最大层间位移角 : 1/2224.(第 3层第 1塔 )
Y 方向最大位移与层平均位移的比值 : 1.20(第 1层第 1塔 )
Y 方向最大层间位移与平均层间位移的比值 : 1.23(第 2层第 1塔 )
=== 工况 3 === 竖向恒载作用下的楼层最大位移
Floor Tower Jmax Max-(Z)
9 1 1053 -2.39
8 1 1009 -3.25
7 1 895 -3.53
6 1 781 -3.77
5 1 667 -3.83
4 1 469 -3.35
3 1 426 -7.19
2 1 250 -1.57
1 1 116 -1.50
=== 工况 4 === 竖向活载作用下的楼层最大位移
Floor Tower Jmax Max-(Z)
9 1 1 -1.14
8 1 1009 -1.10
7 1 895 -1.07
6 1 781 -0.99
5 1 667 -0.92
4 1 469 -0.68
3 1 284 -1.28
2 1 194 -0.21
1 1 91 -0.21
作文四:《土木工程毕业设计外文翻译--土木工程》15200字
本科毕业设计
英 文 翻 译
系 (院) :土木工程 专业方向: 班 学 姓 日 级: 号: 名: 期:
指导教师:
Civil Engineering
Civil engineering is the planning, design, construction, and management of the built environment. This environment includes all structures built according to scientific principles, from irrigation and drainage systems to rocket launching facilities. Civil engineers build roads, bridges, tunnels, dams, harbors, power plants, water and sewage systems, hospitals, schools, mass transit, and other public facilities essential to modern society and large population concentrations. They also build privately owned facilities such as airport, railroads, pipelines, skyscrapers, and other large structures designed for industrial, mercial, or residential use. In addition, civil engineers plan, design, and build plete cities and towns, and more recently have been planning and designing space platforms to self-contained munities. The word civil derives from the Latin for citizen. In 1782, Englishman John Seaton used the term to differentiate his nonmilitary engineering work from that of the military engineers who predominated at the time. Since then, the term civil engineer has often been used to refer to engineers who build public facilities, although the field is much broader. Scope Because it is so broad, civil engineering is subdivided into a number of technical specialties. Depending on the type of project, the skills pf many kinds of civil engineer specialties may be needed. When a project begins, the site is surveyed and mapped by civil engineers who experiment to determine if the earth can bear the weight of project. Environmental specialists study the project’s impact on the local area, the potential for air and groundwater pollution, the project’s impact on local animal and plant life, and how the project can be designed to meet government requirements aimed at protecting the environment. Transportation specialists determine what kind of facilities are needed to ease the burden on local roads and other transportation networks that will result from the pleted project. Meanwhile, structural specialists raise preliminary data to make detailed designs, plans, and specifications for the project. Supervising and coordinating the work of these civil engineer specialists, from beginning to end of the project, are the construction management specialists. Based on information supplied by the other specialists, construction management civil engineers estimate quantities and costs of materials and subcontractors, and perform other supervisory work
1
to ensure the project is pleted on time and as specified. Many civil engineers, among them the top people in the field, work in design. As we have seen, civil engineers work on many different kinds of structures, so it is normal practice for an engineer to specialize in just one kind. In designing buildings, engineers often work as consu
ltants to architectural or construction firms. Dams, bridges, water supply systems, and other large projects ordinarily employ several engineers whose work is coordinated by a system engineer who is in charge of the entire project. In many cases, engineers from other disciplines are involved. In a dam project, for example, electrical and mechanical engineers work on the design of the powerhouse and its equipment. In other cases, civil engineers are assigned to work on a project in another field; in the space program, for instance, civil engineers were necessary in the design and construction of such structures as launching pads and rocket storage facilities. Throughout any given project, civil engineers make extensive use of puters. Computes are used to design the project’s various elements (puter-aided design, or CAD) and to manger it. Computers are a necessity for the modern civil engineer because they permit the engineer to efficiently handle the large quantities of data needed in determining the best way to construct a project. Structural engineering In this specialty, civil engineers plan and design structures of all types, including bridges dams, power plants, supports for equipment, special structures for offshore projects, the United States space program, transmission towers, giant astronomical and radio telescopes, and many other kinds of projects. Using puters, structural engineers determine the forces a structure must resist, its own weight, wind and hurricane forces temperature changes that expand or contract construction materials, and earthquakes. They also determine the bination of appropriate materials: steel, concrete, plastic, stone, asphalt, brick, aluminum, or other construction materials. Water resources engineering Civil engineers in this specialty deal with all aspects of the physical control of water. Their projects help prevent floods, supply water for cities and for irrigation, manage and control rivers and water runoff, and maintain beaches and other waterfront facilities. In addition, they design and maintain harbors, canals, and locks, build huge hydroelectric dams and smaller dams and water impoundments of all kinds, help design offshore structures, and determine the location of structures affecting navigation.
2
Geotechnical engineering Civil engineers who specialize in this filed analyze the properties of soils and rocks that support structures and affect structural behavior. They evaluate and work to minimize the potential settlement of buildings and other structures that stems from the pressure of their weight on the earth. These engineers also evaluate and determine how to strengthen the stability of slopes and how to protect structures against earthquakes and the effects of groundwater. Environmental engineering In this branch of engineering, civil engineers design, build, and supervise systems to provide safe drinking water and to prevent and control pollution of water supplies, both on the sur
face and underground. They also design, build, and supervise projects to control or eliminate pollution of the land and air. These engineers build water and wastewaters treatment plants, and design air scrubbers and other devices to minimize or eliminate air pollution caused by industrial processes, incineration, or other smoke-producing activities. They also work to control toxic and hazardous wastes through the construction of special dump sites or the neutralizing of toxic and hazardous substances. In addition the engineers design and manage sanitary landfills to prevent pollution of surrounding land. Transportation engineering Civil engineers working in this specialty build facilities to ensure safe and efficient movement of both people and goods. They specialize in designing and maintaining all types of transportation facilities, highways and streets, mass transit systems, railroads and airfields ports and harbors. Transportation engineers apply technological knowledge as well as consideration of the economic, political, and social factors in designing each project. They work closely with urban planners since the quality of the munity is directly related to the quality of the transportation system. Pipeline engineering In this branch of civil engineering, engineers build pipelines and related facilities, which transport liquids, gases, or solids ranging from coal slurries (mixed coal and water) and semi liquids wastes, to water, oil and various types pf highly bustible and nonbustible gases. The engineers determine pipeline design, the economic and environmental impact of a project on regions it must traverse, the type pf materials to be used-steel, concrete, plastic, or binations of various materials, installation techniques, methods for testing pipeline strength, and controls for maintaining proper pressure and rate of flow of materials being transported. When hazardous materials are being carried, safety is a major consideration as well. Construction engineering Civil engineers in this field oversee the
3
construction of a project from beginning to end. Sometimes called project engineers, they apply both technical and managerial skills, including knowledge of construction methods, planning, organizing, financing, and operating construction projects. They coordinate the activities of virtually everyone engaged in the work: the surveyors, workers who lay out and construct the temporary roads and ramps, excavate for the foundation, build the forms and pour the concrete; and workers who build the steel frame-work. These engineers also make regular progress reports to the owners of the structure. Construction is a plicated process on almost all engineering projects. It involves scheduling the work and utilizing the equipment and the materials so that coats are kept as low as possible. Safety factor must also be taken into account, since construction can be very dangerous. Many civil engineers therefore specialize in the constr
uction phase. Community and urban planning Those engaged in this area of civil engineering may plan and develop munities within a city, or entire cities. Such planning involves far more than engineering considerations; environmental, social, and economic factors in the use and development of land and natural resources are also key elements. They evaluate the kinds of facilities needed, including streets and highways, public transportation systems, airports, and recreational and other facilities to ensure social and economic as well as environmental well-being. Photogrammetry, surveying, and mapping The civil engineers in this specialty precisely measure the Earth’s surface to obtain reliable information for locating and designing engineering projects. This practice often involves high-technology methods such as satellite and aerial surveying, and puter processing of photographic imagery. Radio signals from satellites, scanned by laser and sonic beams, are converted to maps to provide very accurate measurements for boring tunnels, building highways and dams, plotting flood control and irrigation projects, locating subsurface geologic formations that may affect a construction project and a host of other building uses. Other specialties Three additional civil engineering specialties that are not entirely within the scope of civil engineering teaching. Engineering research Research is one of the most important aspects of scientific and engineering practice. A researcher usually works as a member of a team with other scientists and engineers. He or she is often employed in a laboratory that financed by government or industry. Areas of research
4
connected with civil engineering include soil mechanics and soil stabilization techniques, and also the development and testing of new structural materials. Engineering management Many civil engineers choose careers that eventually lead to management. Others are also to start their careers in management positions. The civil engineer manager bines technical knowledge with an ability to organize and coordinate worker power, materials, machinery, and money. These engineers may work in government municipal, county, state, or federal; in the U.S.Army Corps of Engineers as military or civilian management engineers; or in semiautonomous regional or city authorities or similar organization. They may also manage private engineering firms ranging in size from a few employees to hundreds. Engineering teaching The civil engineer who chooses a teaching career usually teaches both graduate and undergraduate students in technical specialties. Many teaching civil engineers engage in basic research that eventually leads to technical innovations in construction materials and methods. Many also serve as consultants on engineering projects, or on technical boards and missions associated with major projects.
5
土木工程
土木工程是指对建成环境的规划、设计、建造、管理等一系列活动。
所谓建成环境是包括从灌溉、 排水系统到火箭发射设施等所有根据科学原 理而建造的建筑。 土木工程师建造道路、桥梁、隧道、堤坝、海港、发电厂、给水、排 污系统、医院、学校、公共交通以及现代社会和人口高度集中所必需的其 它公共设施。 他们还建造机场、 铁路、 管道、 摩天大楼之类的非公有设施, 以及其它为了工业、商业或居住用途而设计的大型建筑物。此外,土木工 程师还规划、设计和建造完善的都市和城镇,近来又计划和设计能够自给 的空间站。 Civil engineering 中的 civil 一词来源于拉丁文中的 citizen(市民或公 民) 1782 年英国人 John Seaton 使用该词以区别非军用工程与那时占主导 。 地位的军用工程。从那以后,土木工程一词用来指那些建造公共设施的工 程,尽管这一领域越来越广泛。 范围 由于土木工程涉及的范围十分广泛, 因而将其划分为很多技术 专业。根据项目的类型不同,需要许多专业的土木工程专家的技术参与。 项目开始时,土木工程师要进行现场勘探、绘图,通过实验确定该项目所 在土层的承载力。环境专家研究工程项目对本地区的影响,和如何设计工 程项目使其能满足政府对环境保护的要求。 交通运输专家确定需要何种类 型的交通设施以减轻项目完成后对既有道路和交通网络构成的压力。同 时,结构专家为该工程项目搜集原始资料,以进行具体的设计、规划,并 提出该项目的说明书。从工程项目的开始至终结,施工管理专家监督与协 调这些土木工程师的工作。以其它专家所提供的信息为基础,施工管理土 木工程师估计材料与劳动力的数量和价格,安排全部工作计划,订购工作 所需的材料与设备,雇用承包商与转包商,并进行其它监督工作以确保工 程项目能按规定完成。 土木工程领域的很多工程师从事设计工作。正如我们所看到的,土木 工程师的工作涉及多种类型的结构,所以对一个工程师而言,仅在某种结 构上有专长是一种正常现象。在建筑设计时,工程师通常是某个建筑设计 公司或施工企业的顾问。堤坝、桥梁、给水系统和其它大型项目通常聘用 几位工程师,在负责整个项目的系统工程师领导下协同工作。在很多情况 下也会有一些其他专业的工程师参加其中,例如在一个堤坝项目中,电力 工程师和机械工程师会参与发电站的设计与其设备安装。另外,土木工程 师也会被指派为别的领域的项目而工作,例如在实施空间计划时,需要土 木工程师参与诸如火箭发射台和火箭贮存库这些结构的设计和施工。
6
在任何项目的实施过程中,土木工程师都要广泛使用到电脑这种工 具。电
脑被用与工程项目各种要素的设计(计算机辅助设计或称为 CAD) 和控制。 由于计算机使土木工程师能够更为有效的处理和确定项目建造最 佳方式所需的大量数据,因此计算机是现代土木工程师的必需品。 结构工程 在这个专业领域, 土木工程师规划、 设计所有类型的结构, 这些结构包括桥梁、堤坝、动力厂、设备底座、近海工程的特殊结构、美 国空间项目、输电塔、大型的天文和无线电望远镜以及其它很多类型的项 目。 结构工程师使用计算机来确定结构所必须抵抗的力, 即结构本身的重 量、风荷载、温度变化引起的建筑材料膨胀或收缩以及地震。他们还要选 定合适的材料例如钢材、混凝土、塑料、石材、沥青、砖、铝或者其它结 构材料等,并将其组合起来以形成结构。 水利资源工程 这一领域的土木工程师处理所有的水自然控制方面 的问题。他们的工程项目帮助防洪,城市供水和灌溉用水,管理与控制江 河及水的径流量,以及维护海滩和其它沿岸设施。另外,他们还设计和维 修海港、沟渠、水闸,建造巨大的水电堤坝、较小的堤坝和各种类型的蓄 水堤坝, 设计离岸的海上结构物, 以及确定对航行有影响的建筑物的位置。 岩土工程 在这一领域有专长的土木工程师分析支撑建筑和结构特 性的岩土性质, 他们估计并力求减小建筑物和其它构筑物由其作用于岩土 层上的重力而产生的沉降。 这些工程师还要估计并确定如何加强边坡和填 方的稳定性以及如何保护建筑以抵抗地震和地下水的作用。 环境工程 在这一领域中,土木工程师设计、建造和监督安全的饮用 水系统,防止和控制来自地表和地下的对供水系统的污染。他们还设计、 建造和监督能够控制或消除土地和空气污染的工程项目。 这些工程师建造 自来水厂和污水处理厂, 设计空气洗涤器和其它设备以减少或消除由工业 生产、焚化或其它产生烟的行为所引起的空气污染。他们还通过建造特殊 的垃圾场来中和有毒物质等方式来控制有毒的和危险的物质。另外,这些 工程师还设计和管理卫生掩埋场以防止周围土地的污染。 交通运输工程 该领域的土木工程师建造能确保人与货物能安全有 效运转的设施。他们擅长于设计和维修各种类型的交通设施,如公路和街 道、大规模的交通体系、铁路、航空港和海港码头。交通运输工程师在设 计每一个工程项目时要运用科技知识,同时还要考虑经济、政治和社会等 因素。因为社区的质量与交通运输体系的质量有直接的关系,所以他们要 与城市规划者密切协作。 管道工程 在这一领域,工程师铺设管道、建造相关设施,用来输送 液
体、气体或固体,从煤浆(煤与水的混合物) 、半液状的废物到水、油 和各种各样极易燃烧的和不宜燃烧的气体。 这些工程师选定使用材料的类
7
型,例如钢材、混凝土、塑料或多种材料的组合,决定安装技术,并确定 计算管道强度的方法、维持适当压力的调节装置以及被输送物质的流速 等。当输送危险物质时,安全也是应考虑的问题。 建筑工程 这一领域的土木工程师负责监督一个项目从开始到竣工 的施工过程,有时又被称为项目主管工程师。他们的应用技术和管理技能 包括施工方面的知识,计划、组织、筹措资金及经营整个建设项目等。他 们协调几乎每一个参与工作的人员的活动,这些工作人员包括测量员,临 时道路与边坡的放线和修筑工人, 挖掘地基、 支摸板和浇注混凝土的工人, 以及绑扎钢筋骨架的工人。这些工程师还要向项目业主作定期的进度报 告。 几乎所有工程项目的施工过程都很复杂。在施工时要制定工作计划, 合理利用设备与材料, 从而尽可能的降低工程费用。 安全因素也必须考虑, 因为施工过程非常危险,所以需要很多土木工程师从事施工阶段的工作。 社区与城市规划 这一领域的土木工程师负责规划和发展城市中的 社区或整个城市。这些规划远不止于工程面上的考虑,当时环境、社会和 经济因素、土地和天然资源的发展也是主要考虑因素。这些工程师将市政 工程的规划同私人开发的规划相互协调。他们评估各种必要的设施,这些 设施包括街道和公路、公共交通运输系统、民用机场、港口设施、给排水 系统、公共建筑、公园、娱乐设施及其它为了保证社会福利以及经济的、 环境的利益而设置的公共设施。 摄影测量,测绘,和制图 这一领域的工程师测量地球的表面以获得 有利于定位和设计工程项目的可靠信息。 这些工程实践通常涉及到高科技 方法例如卫星和航空测量,摄影成像的计算机处理等。可以把人造卫星传 来的通过激光束与声波扫描得到的无线电信号转变为图象, 以便为开挖隧 道、建造公路与堤坝、描绘防洪灌溉工程、确定影响施工计划的地下地质 构造以及其它许多建筑用途提供精确的测量结果。 其它领域 有三个附加专业,不完全包含在土木工程范围内,但确是 三个基本的学科,那就是工程科研、工程管理和工程教学。 工程科研 科研是科学和实践最为重要的一个方面。 一个研究者通常 是一个科研小组的一员,他要和其他的科学家、工程师一起工作。他们供 职于一个收政府或企业资助的实验室。土木工程科研的领域包括力学、土 稳定性技术、新型结构材料的开发与实验等。 工
程管理 很多土木工程师选择了某种职业, 而这些职业最终通向管 理层,另外一些工程师开始就选择了管理职位的职业生涯。土木工程项目 经理将技术知识与组织协调人力、材料、机械和资金的能力结合起来。他 们可能供职于市、县、轴、联邦政府,或在美国国家工程兵团任军用或民 用工程的管理工程师,或任职于地区或城市的半自治权力机构或类似团
8
体。他们也可能经营私人工程公司,规模从几名到数百名员工不等。 工程教学 选择教师职业的土木工程师通常给攻读工程技术的大学生 或研究生授课。很多从事土木工程教学的工程师还参加一些基础研究工 作,从而推动建筑材料和施工方法的技术革新。很多人会出任工程顾问, 或在一些重要工程项目的技术委员会或考察团里担当顾问。
9
作文五:《土木工程毕业设计外文资料翻译---浅谈土木工程概论》18500字
题 目 浅谈土木工程概论 学 院 土木建筑学院 专 业 土木工程 班 级 学 生 学 号 指导教师
二〇一二年二月二十日
济南大学毕业设计外文资料翻译
Journal of Civil Engineering and Architecture,2008,12(6):41-50
Introduction to Civil Engineering Papers
Cao Yan
Suqianjiangsu 223800 Suqian institute of architectural design,,
Abstract:Civil engineering is a huge subject, but the main is building, building whether in China or abroad, has a long history, long-term development process. The world is changing every day, but the building also along with the progress of science and hair show. The discovery of mechanics, materials update, ever more scientific technology into the building. But before a have tile roofs of the houses, now for fort, different ideas, different scientific, promoted the development of civil engineering, make it more perfect. Key words: Civil engineering; architecture; mechanics; materials
Civil engineering it is to build the kind of engineering collectively. It meant that and "military project" counterparts. In English, the historical process, mechanical Engineering soil carpentry, electrical Engineering, chemical Engineering belongs to Civil Engineering, because they have a practical utility.Introduction to Civil Engineering Papers Civil Engineering for the development of a key role, first as a material foundation for the civil engineering construction materials, followed by the subsequent development of the design theory and construction technology. Every time a new quality of building materials, civil engineering will be a leap-style development.
- 1 -
济南大学毕业设计外文资料翻译
People can only rely on the early earth, wood and other natural materials in the construction activities, and later appeared in brick and tile that artificial materials, so that the first human to break the shackles of natural building materials. China in the eleventh century BC in the early Western Zhou Dynasty created the tile. The first brick in the fifth century BC to the third century BC, when the tomb of the Warring States Period. Brick and tile better than the mechanical properties of soil, materials, and easy to manufacture. The brick and tile so that people began to appear widely, to a large number of housing construction and urban flood control project, and so on. This civil engineering technology has been rapid development.
Up to 18 to the 19th century, as long as two thousand years, brick and tile has been a major civil engineering construction materials, human civilization has made a great contribution to the even was also widely used in the present. The application of a large number of steel products is the second leap in civil engineering. Seventeen 1970s the use of pig iron, the early nineteenth century, the use of wrought iron bridges and the construction of housing, which is a prelude to the emergence of steel. From the beginning of the mid-nineteenth century, metallurgical industry, smelting and rolling out high tensile and pressive strength, ductility, uniformity of the quality of construction steel and then produce high-strength steel wire, steel cables. As a result of the need to adapt to the development of the steel structure have been flourishing.
In addition to the application of the original beam, arch structure, the new truss, a
- 2 -
济南大学毕业设计外文资料翻译
framework, the structure of network, cable structures to promote the gradual emergence of the structure of Yan in the form of flowers. From the brick building long-span structures, stone structures, a few meters of wood, steel structure to the development of tens of meters, a few hundred meters, until modern km above. So in the river, cross the bridge from shelves, on the ground since the construction of skyscrapers andhigh-rise tower, even in the laying of underground railway, to create an unprecedented miracle. In order to meet the needs of the development of steel works, on the basis of Newton's mechanics, material mechanics, structural mechanics, structural engineering design theory came into being, and so on.
Construction machinery, construction technology and construction organization design theory also development, civil engineering from the experience of rising to bee science, engineering practice and theoretical basis for both is a different place, which led to more rapid development of civil engineering. During the nineteenth century, 20, made of Portland cement, concrete has e out. Concrete can aggregate materials,
easy-to-concrete structures forming, but the tensile strength of concrete is very small, limited use. By the middle of the nineteenth century, the surge in steel production, with the emergence of this new type of reinforced concrete posite construction materials, which bear the tension steel, concrete bear the pressure and play their own advantages. Since the beginning of the 20th century, reinforced concrete is widely used in various fields of civil engineering.
From the beginning of the 1930s, there have been pre-stressed concrete. Pre-stressed concrete structure of the crack resistance, rigidity and carrying capacity, much higher than the reinforced concrete structure, which uses an even wider area. Civil Engineering into the reinforced concrete and prestressed concrete dominant historical period. Concrete buildings to bring about the emergence of new economic, aesthetic structure in the form of engineering, civil engineering so that a new construction technology and engineering design of the structure of the theory. This is another leap in the development of civil engineering. A project to build the facilities in general to go through the investigation, design and construction in three stages, require the use of geological prospecting projects, hydro-geological survey, engineering survey, soil mechanics, mechanical engineering, engineering design, building materials, construction equipment, engineering machinery, building the economy , And other disciplines and construction technology, construction and other fields of knowledge, as well as puter and mechanical testing techniques. Civil engineering is therefore a broad range of integrated disciplines. With the progress in science and technology
development and engineering practice, the civil engineering disciplines have also been developed into a broad connotation, the number of categories, the structure of plex integrated system. Civil Engineering is acpanied by the development of
- 3 -
济南大学毕业设计外文资料翻译
human society developed. It works in the construction of facilities reflect the various historical periods of socio-economic, cultural, scientific, technological development outlook, which civil society has bee one of the historical development of the witness. In ancient times, people began to build simple houses, roads, bridges and still water channel to meet the simple life and production. Later, in order to adapt to the war, production and dissemination of religious life, as well as the needs of the construction of the city, canals, palaces, temples and other buildings. Many well-known works shown in this historical period of human creativity.
For example, the Great Wall of China, Dujiangyan, the Grand Canal, Zhaozhou Bridge, Yingxian Wooden Tower, the pyramids of Egypt, Greece's Parthenon, Rome's water supply project, colosseum amphitheater (Rome large animal fighting Field), as well as many other well-known churches, palaces and so on. After the industrial revolution, especially in the 20th century, on the one hand, civil society to put forward a new demand; On the other hand, all areas of society for the advancement of civil engineering to create good conditions. Thus this period of civil engineering has been advanced by leaps and bounds. All over the world there have been large-scale modernization of industrial plants, skyscrapers, nuclear power plants, highways and railways, long-span bridges, and large-diameter pipelines long tunnel, the Grand Canal, the big dams, airports, port and marine engineering, etc. .
For civil engineering continually modern human society to create a new physical environment, human society, modern civilization has bee an important part. Civil Engineering is a very practical subjects. In the early days, through the civil engineering practice, summing up successful experience, in particular, to draw lessons from the failure
- 4 -
济南大学毕业设计外文资料翻译
of developed. From the beginning of the 17th century, with Galileo and Newton as a pilot with the mechanics of the modern civil engineering practice, gradually formed the mechanical, structural mechanics, fluid mechanics, rockmechanics, civil engineering as the basis of theoretical subjects.
This experience in civil engineering from the gradually developed into a science. In the course of the development of civil engineering, engineering practice often first experience in theory, engineering accidents often show a new unforeseen factors, triggering a new theory of the research and development. So far a number of projects dealing with the problem, is still very much rely on practical experience. Civil Engineering Technology with the main reason for the development of engineering practice and not by virtue of scientific experiments and theoretical studies, for two reasons: First, some of the objective situation is too plicated and difficult to faithfully carry out laboratory or field testing and analysis. For example, the foundation, tunnel and underground engineering and deformation of the state and its changes over time, still need to refer to an analysis of engineering experience to judge. Second, only a new engineering practice in order to reveal new problems. For example, the construction of a high-rise buildings, high-rise tower and mast-span bridges, wind and earthquake engineering problems highlighted in order to develop this new theory and technology.
In the long-term civil engineering practice, it is not only building great attention to the arts, has made outstanding achievements; and other works, but also through the choice of
- 5 -
济南大学毕业设计外文资料翻译
different materials, such as the use of stone, steel and reinforced concrete, with natural Environmental art in the construction of a number of very beautiful, very functional and good works. Ancient Great Wall of China, the modern world, many of the television tower and the bridge ramp Zhang, are cases in point.
Use of project management information platform, email, video conference system three system for the project provides a advanced modern information transfer and the means of exchange, make the project information sharing more in time, more agile and more widely, and have the different interactive discussion of the implementation of the environment, involved in the project staff in the world within the scope of the any place convenient check project management information, headquarters staff can also access management of other place orders management information, understand the overall project, through the database, the part of the division, construction site, such as subcontractor closely together, create a distributed collaborative working environment, and can implement different ground mand and control.
Civil engineering information already, include the construction management of information also includes building technology development of information, construction management information should be in the open on the three levels, namely, in civil engineering industry management information, work process project management information, civil engineering enterprise management information. Civil engineering industry management informationization is the root, embodies the characteristics of the industry and business market characteristics of the industry; Civil engineering enterprise informationization is the rod, must be made to build in industry deep understanding, must meet the industry to run the rule; Engineering information is fruit.
Civil engineering information construction to adjust the structure of industries and enterprises and of the three conditions "bined, and enterprise's scientific management, technological progress, and the bination of using the global information industry promotion experience, learn the line of informatization construction of results from industry, enterprise and engineering practice, the research development general solutions and individual solutions, ply with" government to promote and market guide, enterprise's main body, industry breakthrough, regional development, steadily promoting "the policy, give full play to the colleges and universities, research institutes role, especially related to learn will, association continuous innovation, trying to make with civil engineering the information construction walked into the new era, give full play to the cross-trade and cross department experts assemble advantage, make new contribution.
- 6 -
济南大学毕业设计外文资料翻译
References 参考文献
Jinwu et al.2007. Civil engineering structure design wind resistance. Beijing: science press.
Xikang et al. 2000Civil engineering construction. Beijing: China building materials ndustry press. i
XingHuaYan, XinHuang 2005. Civil engineering introduction. Beijing. People's traffic press.
DuanShuJin et al. 2005. Civil engineering introduction. Beijing. China railway publishing house.
John S. Scott, 1991,Dictionary of Civil Engineering, 4th Edition, Penguin Books Publisher
R. S. Narayanan & A. W. Beeby, 2001.Introduction to Design for Civil Engineers, , Spon Press.
Y. Xiao & J.C. Anderson.2007 .Design of Steel Structures, Higher Education Press.
XueZhongWu et al.2009 . Civil engineering present situation and the development trend analysis [J]; Modern trade industry.
YuLiu et al.2010 . Civil engineering present situation and the development trend of the [J]; Heilongjiang science and technology information.
ZhengHuaXu;PangJunWei; 2007. Civil engineering construction of informatization [J]; Coastal enterprise and science and technology.
PengJianGuo; Jing wang et al 2009. Information construction of civil engineering [J]; Heilongjiang science and technology information.
Wei Chen et al. 2008. Training of the 21 st century civil engineering application talents [J]; Sichuan architecture.
- 7 -
济南大学毕业设计外文资料翻译
《土木工程与建筑》,2008,12(6):41-50
浅谈土木工程概论
曹燕
(江苏省宿迁市正宏城建设计研究院,宿迁223800) 摘 要:土木工程是个庞大的学科,但最主要的是建筑,建筑无论是在中国还是在国外, 都有着悠久的历史,长期的发展历程。整个世界每天都在改变,而建筑也随科学的进步而发展。力学的发现,材料的更新,不断有更多的科学技术引入建筑中。以前只求一间有瓦盖顶的房屋,现在追求舒适,不同的思想,不同的科学,推动了土木工程的发展,使其更加完美。
关键词:土木工程;建筑;力学;材料。
土木工程它是建造各 种工程的统称。它的原意是与“军事工程”相对应的。在英语中,历史上土木工 程、机械工程、电气工程、化工工程都属Civil Engineering,因为它们都具 有民用性。对土木工程的发展起关键作用的, 首先是作为工程物质基础的土木 建筑材料,其次是随之发展起来的设计理论和施工技术。每当出现新 的优良的建筑材料时,土木工程就 会有飞跃式的发展。
人们在早期只能依靠泥土、木料及其它天然材料从事营造活动,后 来出现了砖
- 8 -
济南大学毕业设计外文资料翻译
和瓦这种人工建筑材料, 使人类第一次冲破了天然建筑材 料的束缚。中国在公元前十一世纪 的西周初期制造出瓦。最早的砖 出现在公元前五世纪至公元前三世纪战国时的墓室中。 砖和瓦具有比 土更优越的力学性能,可以就地取材,而又易于加工制作。 砖和瓦的出现使人们开始广泛地、大量地修建房屋和城防工程等。 由此土木工程技术得到了飞速的发展。
直至 18,19 世纪,在长达两 千多年时间里,砖和瓦一直是土木工程的重要建筑材料,为人类文明 作出了伟大的贡献,甚至在目前还被广泛采用。钢材的大量应用是土木工程的第二次飞跃。十七世纪 70 年代开始 使用生铁、十九世纪初开始使用熟铁建造桥梁和房屋,这是钢结构出 现的前奏。 从十九世纪中叶开始,冶金业冶炼并轧制出抗拉和抗压强度都很高、 延性好、质量均匀的建筑钢材,随后又生产出
于是适应发展需要的钢结构得到蓬勃发展。 高强度钢丝、钢索 。
除应用原有的粱、拱结构外,新兴的桁架、框架、网架结构、悬索结构逐渐推广,出现了结构 形式百花争艳的局面。 建筑物跨径从砖结构、石结构、木结构的几米、几十米发展到钢结构的百米、几百米,直到现代的千米以上。于是在大江、海峡上架 起大桥,在地面上建造起摩天大楼和高耸铁塔,甚至在地面下铺设铁 路,创造出前所未有的奇迹。为适应钢结构工程发展的需要,在牛顿力学的基础上,材料力学、 结构力学、工程结构设计理论等就应运而生。
- 9 -
济南大学毕业设计外文资料翻译
施工机械、施工技术和 施工组织设计的理论也随之发展,土木工程从经验上升成为科学,在工程实践和基础理论方面都面貌一新, 从而促成了土木工程更迅速的发展。 十九世纪 20 年代,波特兰水泥制成后,混凝土问世了。混凝土骨料可以就地取材,混凝土构件易于成型,但混凝土的抗拉强度很小,用途受到限制。 十九世纪中叶以后,钢铁产量激增,随之出现了钢 筋混凝土这种新型的复合建筑材料,其中钢筋承担拉力,混凝土承担 压力,发挥了各自的优点。 二十世纪初以来,钢筋混凝土广泛应用 于土木工程的各个领域。
从三十年代开始,出现了预应力混凝土。预应力混凝土结构的抗裂性能、刚度和承载能力,大大高于钢筋混凝土结构,因而用途更为 广阔。 土木工程进入了钢筋混凝土和预应力混凝土占统治地位的历史时期。 混凝土的出现给建筑物带来了新的经济、 美观的工程结构形式, 使土木工程产生了新的施工技术和工程结构设计理论。 这是土木工程 的又一次飞跃发展。 建造一项工程设施一般要经过勘察、设计和施工三个阶段,需要 运用工程地质勘察、水文地质勘察、工程测量、土力学、工程力学、 工程设计、建筑材料、建筑设备、工程机械、建筑经济等学科和施工 技术、施工组织等领域的知识 ,以及电子计算机和力学测试等技术。
- 10 -
济南大学毕业设计外文资料翻译
因而土木工程是一门范围广阔的综合性学科。 随着科学技术的进步和工程实践的发展,土木工程这个学科也已发展成为内涵广泛、门类众 多、结构复杂的综合体系。土木工程是伴随着人类社会的发展而发展起来的。 它所建造的工 程设施反映出各个历史时期社会经济、 文化、 科学、 技术发展的面貌, 因而土木工程也就成为社会历史发展的见证之一。 远古时代,人们就开始修筑简陋的房舍、道路、桥梁和沟澶,以 满足简单的生活和生产需要。后来,人们为了适应战争、生产和生活 以及宗教传播的需要,兴建了城池、运河、宫殿、寺庙以及其他各种 建筑物。名的工程设施显示出人类在这个历史时期的创造力。
例如, 中国的长城、都江堰、大运河、赵州桥、应县木塔,埃及的金字塔, 希腊的巴台农神庙,罗马的给水工程、科洛西姆圆形竞技场(罗马大 斗兽场),以及其他许多著名的教堂、宫殿等。产业革命以后,特别是到了 20 世纪,一方面社会向土木工程提出 了新的需求;另一方面,社会各个领域为土木工程的前进创造了良好 的条件。因而这个时期的土木工程得到突飞猛进的发展。在世界各地 出现了现代化规模宏大的工业厂房、摩天大厦,核电站、高速公路和 铁路、大跨桥梁、大直径运输管道长隧道、大运河、大堤坝、大飞机 场、大海港以及海洋工程等等。
现代土木工程不断地为人类社会创造 崭新的物质环境,成为人类社会现代文明的重要组成部分。 土木工程是具有很强的实践性的学科。在早期,土木工程是通过 工程实践,总结成功的经验,尤其是吸取失败的教训发展起来的。从17 世纪开始,以伽利略和牛顿为先导的近代力学同土木工程实践结 合起来,逐渐形成材料力学、结构力学、流体力学、岩体力学,作为 土木工程的基础理论的学科。
这样土木工程才逐渐从经验发展成为科 学。 在土木工程的发展过程中,工程实践经验常先行于理论,工程事 故常显示出未能预见的新因素,触发新理论的研究
- 11 -
济南大学毕业设计外文资料翻译
和发展。至今不少 工程问题的处理,在很大程度上仍然依靠实践经验。 土木工程技术的发展之所以主要凭借工程实践而不是凭借科学试 验和理论研究,有两个原因:一是有些客观情况过于复杂,难以如实 地进行室内实验或现场测试和理论分析。例如,地基基础、隧道及地 下工程的受力和变形的状态及其随时间的变化, 至今还需要参考工程 经验进行分析判断。 二是只有进行新的工程实践, 才能揭示新的问题。 例如,建造了高层建筑、高耸塔桅和大跨桥梁等,工程的抗风和抗震 问题突出了,才能发展出这方面的新理论和技术。
在土木工程的长期实践中,人们不仅对房屋建筑艺术给予很大注 意,取得了卓越的成就;而且对其他工程设施,也通过选用不同的建 筑材料,例如采用石料、钢材和钢筋混凝土,配合自然环境建造了许 多在艺术上十分优美、功能上又十分良好的工程。古代中国的万里长 城,现代世界上的许多电视塔和斜张桥,都是这方面的例子。
利用项目管理信息平台、电子邮件、视频会议系统三种体系,为项目提供 了一种先进的现代化信息传递和交换手段,使项目信息共享更及时、更灵活、更 广泛,并具备了实施异地交互讨论的环境,参与项目的人员在世界范围内的任何 地方都可以方便的查看项目管理信息,总部管理人员也可以同时访问其他地方项 目管理信息,随时了解项目总体情况,通过这个数据库把公司本部、公司分部、 施工现场、分包商等紧密地联系在一起,创造了一个异地协同工作的环境,并可 实施异地指挥和控制。
- 12 -
济南大学毕业设计外文资料翻译
土木工程的信息化,既包括建筑管理的信息化也包括建筑技术开发的信息 化,建筑管理的信息化应在三个层次上展开,即在土木工程行业管理信息化、工 程项目管理信息化、土木工程企业管理信息化。土木工程行业管理信息化是根,体现了行业的经营特性和行业的市场特点; 土木工程企业信息化是杆,必须建 立在对行业深层次的了解上,必须符合行业运作规律; 工程信息化是果。
土木工程信息化建设要与产业的结构调整和企业的 “三改一加强” 相结合, 与企业的科学管理、技术进步相结合,要借鉴全球信息产业推进的经验,学习各 行各业推进信息化建设成果,从产业、企业和工程实际出发,研究开发一般解决 方案和个别解决方案,遵照“政府推进、市场引导、企业主体、行业突破、区域 展开、稳步推进”的方针,充分发挥大专院校、科研院所的作用,特别是相关学 会、 协会要不断开拓创新, 努力使自己伴随着土木工程的信息化建设走进新时代, 充分发挥跨行业、跨部门专家荟萃的优势,做出新的贡献。
参考文献
吴瑾等编. 土木工程结构抗风设计. 北京:科学出版社,2007
阎西康主编.土木工程施工.北京:中国建材工业出版社,2000
阎兴华,黄新主编. 土木工程概论. 北京. 人民交通出版社,2005
段树金主编. 土木工程概论. 北京. 中国铁道出版社,2005 John S. Scott,土木工程的词典,第四版,1991年,企鹅图书出版商 R. S. Narayanan & A. W. Beeby, 介绍土木工程师设计,2001年,Spon出版社 薛中武;土木工程现状与发展趋势分析[J];现代商贸工业;2009年24期
- 13 -
济南大学毕业设计外文资料翻译
刘瑜;土木工程现状与发展趋势研究[J];黑龙江科技信息;2010年21期
徐正华;庞军伟;土木工程信息化建设研究[J];沿海企业与科技;2007年10期
彭建国;王晶;土木工程的信息化建设[J];黑龙江科技信息;2009年11期
陈伟;培养面向21世纪的土木工程应用型人才[J];四川建筑;2008年02期
- 14 -
作文六:《土木工程施工-绪论》1200字
土木工程施工
授课教师:徐峰
Mail: Tel: 62933091
木兰楼A827
课程教学网站课程学
工程管理研究所网站 教学活动?本科生课程?土木工程施工教学资料
教材与参考书籍
教材
–《土木工程施工(第2版)》应惠清编著高等教育出版社ISBN:9787040262933 参考书籍
–《现行建筑施工规范大全(修订缩印本)现行建筑施工规范大全(修订缩印本)》》中国建筑工业出版社ISBN:7ISBN:7--112-112-07499-07499-1–上海市建筑工程预算定额/ 综合预算定额–上海市装饰工程预算定额
教学安排
《土木工程施工》土木工程施工》课程
–第六学期1~16周
–成绩构成:成绩构成
?平时成绩50%:考勤、课堂讨论、课后作业、小测验、课程设计
?考试成绩50%
–考试:
?内容:课堂教学、作业
?形式:闭卷笔试
教学安排
《土木工程施工土木工程施工》》课程设计:课余完成课程设计课余完成
–准备:自学教材第13章施工组织设计、第12章网络计划技术
–内容:施工组织设计书之施工方案、进度计划–分组:5~6人一组,每组一套施工图纸,共10套–格式:格式:××××××××××工程施工组织设计书模板工程施工组织设计书模板–要求:每2周组长汇报周组长汇报一次进度次进度
–
第16周周四上交打印版和电子版
课程设课程设计
施工方案设计
–划分施工层、施工段,确定施工流向–划分施工过程(工序操作)
–确定施工顺序
–确定关键技术路线
–选择施工方法与施工机械
课程设课程设计
编制施工计划编制计划
–工程量计算表
–施工过程持续时间计算表
–编制施工进度计划————MS ProjectMSMS ProjectProject软件–编制资源计划
施工平面图(了解)
工程质量安全保证措施(了解)
施工组织设计基础资料设础资
设计资料——包括已批准的设计任务书、初步设计(或扩大初步设计)施工图样和设计说明书等初步设计)、施工图样和设计说明书等。
自然条件资料——包括地形、工程地质、水文地质和气象资料。
技术经济条件资料——包括建设地区的建材工业及其产品、资源、供水、供电、交通运输、生产、生活基地设施等资料。 施工合同规定的有关指标——包括建设项目的交付使用日期,包括建设项目的交付使用日期施工中要求采用的新结构、新技术和有关的先进技术指标等。 施工企业及相关协作单位可配备的人力、机械、设备和技术状况,以及施工经验等资料。
国家和地方有关现行规范、规程和定额标准等资料。
单位工程施工组
织设计的编制程
序
《土木工程施工土木工程施工》木程施》课程教学安排 课堂教学:32学时
–绪论
–流水施工
–土石方工程
–桩基础与地下工程
–钢筋砼工程
–结构吊装与桥梁工程
–自学:砌体工程、脚手架工程、预应力砼工程、钢结构工程、装饰工程、防水工程、施工组织设计、网络计划等
相关学科
土力学与地基基础 钢筋砼与砌体工程 机械工程
建筑材料
数学和力学 工程估价
项目管理
运筹学与管理学2014/2/27上海交大徐峰11综合运用
课程特点
实践性 经验性 科学性 创新性2014/2/27上海交大徐峰12
作文七:《绪论土木工程法规概论》1700字
绪论 土木工程法规概论
第一节 土木工程法规的范畴
一、土木工程的特性
1.土木工程定义
在我国对“土木工程”没有严格的法律定义,具有“建设工程、建筑工程、土木工程、??”不统一的名称。
建设部、交通部、铁道部、能源部、航天部 等各个管理职能部委,在工程建设方面的称谓表现不一致。
建设工程,是指土木工程、建筑工程、线路管道和设备安装工程及装修工程(建设工程质量管理条例第2条)。
2.土木工程的范围
(1)建筑:工业和民用房屋 ―― 建造、改造、装饰和装修
(2)市政、公路:道路、桥梁、隧道、公路
(3)水利、电力:堤坝、码头、河道、电厂、输电线路
(4)配套:水、电、煤、通讯、消防、污水、??线路管道的敷设、安装
3.土木工程的活动表现
(1)投资、运作、管理
(2)勘察、设计
(3)施工
(4)监理
(5)运行、保养
4.土木工程的活动特点
(1)项目的固定性
(2)生产和交易的交织性
(3)生产过程的唯一性
5.土木工程活动的参与主体
(1)政府管理部门
(2)投资开发、代理、银行
(3)勘察设计、施工、监理等企业
(4)养护、物业管理 企业
(5)使用者
二、土木工程的法规概况
1.土木工程法规的形式
(1)法律——由全国人民代表大会审议通过,以主席令的方式公布施行;
(2)(国家)管理条例——由国务院常务会议通过,以国务院令的方式发布施行;
(3)(部委)管理办法——由国家部委(如建设部)常务会议通过,发布施行;
(4)(地方)法规——由地方人民代表大会通过,发布施行;
(5)土木工程法规的动态变化和发展。
2.土木工程主要法规的名称
(1)《中华人民共和国民法通则》1986.4.12公布、1987.1.1执行;
(2)《中华人民共和国建筑法》1997.11.1通过,于1998.3.1起施行;
(3)《中华人民共和国合同法》1999.3.15通过,于1999.10.1起施行;
(4)《中华人民共和国招标标法》1999.8.30通过,于2000.1.1起施行;
(5)其他相关法律:《中华人民共和国仲裁法》、《中华人民共和国民事诉讼法》、《中华人民共和国公证暂行条例》、《担保法》、《保险法》、《环境噪音污染防治法》、《文物保护法》、《标准化法》等;
(6)其他相关法规:《建设工程质量管理条例》2000.1.30(国务院279令)、《房屋建筑工程和市政基础设施工程竣工验收备案管理暂行办法》2000.4.7(建设部78令)、《国家工商行政管理局合同鉴证办法》1997.11.3(国家工商局80令)等;
(7)建设工程各类技术方面的《规范》、《规程》、《规定》。
三、土木工程法规的特性
1.土木工程法规的社会关系表现
(1)行政管理关系
(2)经济协作关系
(3)民事关系
2.土木工程法规的基本特征
(1)行政隶属性
(2)经济性
(3)政策性
(4)技术性
3.土木工程法规的作用
(1)规范建筑行为
(2)保护合法行为
(3)打击违法行为
第二节 土木工程的法律关系
一、概念与特征
1.法律关系的含义
法律关系的含义就是“权利、义务” 的关系。
2.土木工程的法律关系
(1)由土木工程法规中确认和调整的
(2)在土木工程活动中所产生的“权利、义务”的关系
3.土木工程法律关系的特征
(1)综合性(行政法律、民事法律、技术法规)
(2)复杂性(土木工程活动的复杂性、涉及面广、内容繁多)
(3)国家计划的指令性
(4)行政法律的决定性
二、法律关系的构成要素
1.法律关系的三要素:
主体、客体、内容
2.土木工程法律关系的主体
(1)国家机关:权利机关――人民代表大会
行政机关――a)国家计划机关
b)国家建设主管机关 c)国家建设监督机关 d)建设各业务主管机关
(2)社会组织:投资建设方
勘察、设计单位
施工企业
监理、审计、招投标代理等单位
银行
(3)个人
3.土木工程法律关系的客体
土木工程的对象,权利、义务所指向的事务
表现在: a)财(建设资金、货币)
b)物(建筑物、材料、设备、机械)
c)行为(勘察设计、施工安装、监理、等活动) d)非物质财富(方案、专利 等)
4.土木工程法律关系的内容
建设权利、建设义务 的具体表现。
本章作业练习(或案例)
1. 土木工程的法律关系是通过什么形式来体现的?
2、在土木工程法律法规范畴中,哪些可以成为法律客体?
作文八:《土木工程毕业设计致谢》600字
参考文献
1、参考书:
《钢筋混凝土与砌体结构》教材
《建筑力学(下)》教材
《建筑地基与基础》教材
2、国家标准、规范、规程:
《房屋建筑制图统一标准》(GBJ50001-2001) 《建筑结构制图标准》(GBJ50105-2001) 《建筑结构荷载规范》(GB50009-2001) 《混凝土结构设计规范》(GB50010-2002) 《建筑地基基础设计规范》(GB50007-2001) 3、图集:
《中南地区标准图集》
致谢
经过一个多月的时间,我如期完成了题为“南宁市某厂加工车间框架结构设计”的毕业设计。在设计期间,我碰到了各种专业的问题,都及时得到了老师和同学们的正确解答。在没有规范参考的情况下,指导老师给我们复印了一些规范资料进行参照与分析,并且详细地给我们介绍设计的每一步骤,耐心讲解了如何运用力学的知识计算结构的荷载、内力以及配筋。最后在使用PKPM结构设计辅助软件设计结构时,指导老师们不仅在课上传授我们软件知识,并且课余时还亲自到宿舍进一步详细指导。除此之外,同学们之间也非常热心地互相帮助,都能够把自己所掌握的知识传授给我。
通过本次综合毕业设计,使我巩固了两年多以来在学校所学的专业知识,并且还从中学到了一些新的建筑结构知识,以及了解和掌握了如何使用PKPM结构设计辅助软件。再此,我要对指导本次毕业设计的徐红波、王新、杜静老师深表感谢,与此同时,还要感谢帮助过我的同学们,谢谢你们对我热情和耐心的指导~今后我会将我的所学,一如继往地努力回报于社会。
作文九:《土木工程毕业设计办公楼设计》24200字
目 录
摘 要 ...................................................................................................... 3 ABSTRACT ........................................................ 错误!未定义书签。
1 前 言 ............................................................... 错误!未定义书签。
2 建 筑 设 计 . ..................................................................................... 4 2.1建筑概况 .......................................................................................................................... 4 2.2采光、通风、防火设计 .................................................................................................. 4 2.3建筑细部设计 .................................................................................................................. 4 2.4方 案 构 思 . ..................................................................................................................... 4 2.5设 计 过 程 . ..................................................................................................................... 5
2.6建筑做法 .......................................................................................................................... 5
3 结 构 设 计 . ..................................................................................... 5 3.1结构选型布置及计算简图 . ............................................................................................. 6 3.1.1.结构选型 . ............................................................................................................... 6 3.1.2.柱网布置 . ............................................................................................................... 6 3.1.3.梁板柱的截面尺寸 . ............................................................................................... 6 3.1.4. 计算简图 . .................................................................................................................. 7 3.2荷载计算 . ......................................................................................................................... 8 3.2.1. 恒荷载计算 . ........................................................................................................... 8 3.2.2活荷载计算 . ............................................................................................................ 14 3.2.3. 风荷载计算 . ............................................................................................................ 16 3.3. 内力计算 ........................................................................................................................ 17 3.3.1风荷载作用下的内力计算及侧移验算 . ................................................................ 17 3.3.1.1柱的侧移刚度计算过程如下 . ............................................................................. 17 3.3.2. 活荷载作用下的框架内力分析 . ............................................................................ 22 3.3.3. 恒荷载作用下的内力分析 . .................................................................................... 28
3.5. 截面设计 ........................................................................................................................ 37 3.5.1框架梁 . .................................................................................................................. 37 3.5.2. 框架柱 . .................................................................................................................... 46 3.5.3.楼梯的计算 . ......................................................................................................... 51 3.5.4.板的计算 . ............................................................................................................. 54
3.5.5.基础设计 . ............................................................................................................. 59
4施 工 设 计 . ................................................................................... 65 4.1工程概况 . ....................................................................................................................... 65 4.1.1总体概况 . ................................................................................................................ 65 4.1.2建筑设计 . ................................................................................................................ 65 4.1.3结构设计 . ................................................................................................................ 66 4.2施工部署 . ....................................................................................................................... 67 4.2.1总体部署 . ................................................................................................................ 67 4.2.2工程的管理组织 . .................................................................................................... 67 4.3施工准备 . ....................................................................................................................... 68 4.4施工顺序 . ....................................................................................................................... 68 4.4.1施工原则 . ................................................................................................................ 68 4.4.2基础工程施工顺序 . ................................................................................................ 68 4.4.3主体工程施工顺序 . ................................................................................................ 69 4.4.4屋面工程施工顺序 . ................................................................................................ 69 4.5分项工程施工技术及参数 ............................................................................................ 69 4.5.1土方与基础工程施工方案 . .................................................................................... 69 4.5.2主体结构施工方案 . ................................................................................................ 74 4.5.3主要装饰工程施工方案 . ........................................................................................ 84 4.6施工进度计划 . ............................................................................................................... 88 4.7主要机具表 . ................................................................................................................... 89 4.8施工平面图布置 . ........................................................................................................... 89 4.8.1施工平面图布置原则 . ............................................................................................ 89
4.9施工措施 . ....................................................................................................................... 90 4.9.1安全技术措施 . ........................................................................................................ 91 4.9.2文明施工措施 . ........................................................................................................ 93 4.9.3雨季施工措施 . ........................................................................................................ 94 谢 辞 ................................................................... 错误!未定义书签。 参考文献 ............................................................. 错误!未定义书签。
2 建 筑 设 计
2.1建筑概况
该办公楼为四层钢筋框架结构体系,建筑面积约 4000m 2,建筑物平面为矩形。标 准层高 3.6m ,顶层层高 4.2m ,室内外高差 0.45m ,其它轴网尺寸等详见平面简图。 建筑等级 :耐火等级为Ⅱ级
抗震等级为四级
设计使用年限 50年
2.2采光、通风、防火设计
1. 采光、通风设计
在设计中选择合适的门窗位置,取得良好的效果以便于通风。
2. 防火设计
本工程耐火等级为二级,建筑的内部装修、陈设均应做到难燃化,以减少火灾的 发生及降低蔓延速度,公共安全出口设有两个,可以方便人员疏散。楼梯间应采用封 闭式,防止烟火侵袭。在疏散门处应设有明显的标志。各层均应设有手动、自动报警 器及高压灭火水枪。
2.3建筑细部设计
1、 建筑热工设计应做到因地制宜, 保证室内基本的热环境要求, 发挥投资的经济效益。
2、建筑体型设计应有利于减少空调与采暖的冷热负荷,做好建筑围护结构的保温和隔 热,以利节能。
3、采暖地区的保温隔热标准应符合现行的《民用建筑节能设计标准》的规定。
4、室内应尽量利用天然采光。
5、为满足防火和安全疏散要求,在建筑中间有一部楼梯。
6、 商场内的布置与装修以清新自然为主, 卫生间的地面铺有防滑地板砖, 墙面贴瓷砖。 2.4方 案 构 思
设计采用目前国内通用的钢筋混凝土结构。本设计为总体规划中的单体建筑,设 计中充分考虑到总体规划提出的要求、建筑高度、抗震设防烈度和周围环境的关系, 确定本结构为规则有序的板式结构,建筑平面布置简单、规则、对称、长宽比不大, 对抗震有利,结构具有较好的整体性;同时考虑到结构不同使用功能的需求,建筑平 面布置较为灵活,可以自由分割空间,选用框架结构;立面注意对比与呼应、节奏与 韵律,体现建筑物质功能与精神功能的双重特性。
2.5设 计 过 程
建筑设计根据建筑用地条件和建筑使用功能、周边城市环境特点,首先设计建筑 平面,包括建筑平面选择、平面柱网布置、平面交通组织及平面功能设计;其次进行 立面造型、剖面设计;最后设计楼梯和卫生间。本设计满足建筑单位的使用要求,技 术措施合理,同时,通风、采光、消防等技术指标均满足相应的规范和规定。
2.6建筑做法
1.屋面做法:防水、保温层:60mm 厚现场喷涂硬质发泡聚氨脂;
找坡层:1:8水泥膨胀珍珠岩找坡 2%最薄处 40厚;
结构层:120mm 厚钢筋砼屋面板。
2.楼面做法 :地面:10厚铺地砖;
结构层:100㎜现浇砼板。
3.墙体做法:内墙:喷涂料;
7厚 1:0.3:3 水泥石灰膏砂浆抹面压实抹光;
8 厚 1:1:6 水泥石灰膏砂浆扫毛;
8厚 1:3 水泥石灰砂浆打底扫毛;
加气混凝土界面处理剂一道。
外墙:7厚 1:2.5水泥浆抹面;
9厚 1:1:6水泥石灰膏砂浆找平扫毛;
7厚 1:3 水泥砂浆打底扫毛;
素水泥界面处理剂一道。
图 2.1标准层平面图
3 结 构 设 计
3.1 结构选型布置及计算简图
3.1.1.结构选型
本工程选用钢筋混凝土框架结构
选择此结构的原因:
由设计任务书中的要求,要求建筑物内部使用空间能灵活分割,采用框架结构即可 最大限度的满足任务书中的要求。
钢筋混凝土框架结构体系,结构整体性好,抗震性能好。
3.1.2.柱网布置
图 3.1 柱网布置图
3.1.3.梁板柱的截面尺寸
3.1.3.1梁
a .框架梁:L=9600mm 梁高 h=(1/12-1/18)L=(800-533)mm
取 h=750mm
梁宽 b=(1/3-1/2)h=(250-375) mm 取 b=350mm
b . 次梁 :由于次梁支撑条件不好,故可取次梁尺寸:b× h=350×750 mm
c .跨中梁 :L=2400mm, 取 b=350mm, h=400mm
3.1.3.2 板跨 L=4800 此处取板厚取 h=140mm
3.1.3.3 柱
柱的尺寸根据轴压比公式确定
μ=N/fcbh
a. 边柱, q 取 13kN/m2
μ=1.05 , fc=14.3 N/mm2
A1=(6.9/2+4.8)*8.7/2=35.888 m2
N1= A1q=35.888×13=466.544KN
设计值 N1=1.25×N1×n=1.25×466.544×4=2332.688 kN
柱截面面积 A=N/fcμ=155357 mm2
则 b=h=394mm
取柱截面尺寸为 b×h=400×400mm
b. 中柱:
A2=(6.9/2+4.8) ×(1.2+8.7/2) =48.563 m2
N2=A2q=48.563×13=631.313KN
设计值 N=1.25×N2×n=125×631.313×4=2976.188 KN
则柱截面积 A= N/fcμ=189204mm 2
则 b=h=435mm
取柱的截面尺寸为 b×h=450×450mm
3.1.4. 计算简图
结构计算简图如图所示,室内外高差为 450mm ,根据地质资料确定基础顶面离 室外地面为 600mm 。因此求得底层计算高度为 0.6+0.45+3.6=4.65m。各梁柱构件的线 刚度比经过计算后列于图中其中在求梁截面惯性矩时考虑到现浇楼板的作用,取 I=2Io(Io为不考虑楼板翼缘作用的梁截面惯性矩 ) 。
主梁
Ib1=2 Ec×(1/12) ×0.4×0.753 /8.475=2.90×3310Ecm -
上部二、三层边柱
1边 c i =Ec×
(1/12) ×0.44 /3.6=5.9×3410Ecm - 顶层边柱
2边 c i =1边 c i ×
3.6/4.2=5.1×3410Ecm - 上部二、三层中柱
1中 c i =Ec×
(1/12) ×0.454 /3.6=9.5×10-43410Ecm - 顶层中柱
2中 c i =1中 c i ×
3.6/4.2=8.1 ×3410Ecm - 底层中柱
3中 c i =1中 c i ×
3.6/4.65=7.4×3410Ecm - 顶层边柱
3边 c i =1边 c i ×
3.6/4.65=4.6×3410Ecm -
图 3.2结构计算简图(3410Ecm -)
3.2 荷载计算
3.2.1. 恒荷载计算
3.2.1.1 屋面框架梁线荷载标准值
20厚 1:3水泥砂浆抹平 1×1m 分格 0.02×20=0.4kN/m2 60厚现场喷涂硬质发泡聚氨酯保温防水层 0.06×1=0.06 kN/m2 1:8水泥膨胀珍珠岩找坡 2%最薄处 40厚 7×0.19=1.33kN/m2 140厚现浇钢筋混凝土屋面板 0.14×25 = 3.5 kN/m2 楼面抹灰及吊顶 0.35kN/m2
屋面恒荷载 5.61kN/m2
横向框架梁自重 : 0.75×0.35×25=6.56kN/m
则作用在屋顶框架梁上的线荷载为:
梁
q =6.56kN/m
板
q = 4.8×5.61=26.93kN/m
3.2.1.2楼面框架梁线荷载标准值
10厚铺地砖稀水泥填缝 :28×0.01=0.28 KN/m2
25厚 1:2干硬性水泥砂浆结合层:0.025×20=0.5 KN/m2
140厚现浇混凝土楼板 0.14×25=3.5 KN/m2
吊顶荷载 0.35 KN/m2
楼面其他荷载折合成均布荷载 0.5 KN/m2
楼面恒荷载 5.13 KN/m2
横向框架梁自重 6.56KN/m
因此,作用在中间层框架梁上的线荷载为:
梁
q = 6.56kN/m
板
q =4.8×5.13 =24.62kN/m
3.2.1.3屋面框架节点集中荷载标准值
女儿墙自重标准值:600mm 高 200mm 厚,双面抹灰加气混凝土墙自重 0.6×(0.2×7+0.04×20)=1.32KN/m
纵向框架梁自重标准值:0.75×0.35×25=6.56KN/m
次梁自重标准值:0.75×0.35×25=6.56KN/m
图 3.3均布荷载传递图 a.A 轴纵向框架梁传来荷载的标准值 集 A G 4
女儿墙自重: 1.32×7.2=9.50 kN
纵向框架梁自重: 6.56×4.8=31.49 kN
次梁自重: 6.56×8.7×0.5=28.54 kN
屋面恒荷载传来:
()[]KN 88. 9061. 5234. 28. 4212/7. 84. 22/7. 84. 22
1=??????????++-?? KN G A 42. 1604=集
b.B 轴纵向框架梁传来恒荷载标准值 集 B G 4
纵向框架梁自重: 6.56×4.8=31.49 KN
次梁自重 : 6.56×8.7×1/2=28.54 KN
屋面恒荷载传来:
()KN 35. 13961. 54. 28. 422/4. 22/17. 84. 22/7. 82. 72. 1=???
???????+??+-+? KN G B 38. 1994=集
由建筑图知, mm e e D A 50==; mm e B 25=
墙体偏心产生的附加弯矩:m KN M ?=?=71. 0075. 050. 9附加 (其中:附加 e =75mm。 ) 得 M A =MD =160.42×0.050+0.71=8.73 kN.m m KN M B ?=?=98. 4025. 038. 199
3.2.1.4楼面框架节点集中荷载标准值
纵向墙体砌块面密度: 7×0.2=1.4kN/m2
水泥石灰膏砂浆(压实、抹光、扫毛)面密度:(0.007+0.008) ×17=0.225kN/m2 水泥砂浆打底扫毛: 0.008×20=0.16kN/m2 水泥浆(抹面 +打底扫毛)面密度: 0.014×20=0.28kN/m2 水泥石灰膏砂浆面密度: 0.009×17=0.153 kN/m2 则 A 轴墙体面密度 : 0.225+0.16+15+0.28+0.153=2.2 kN/m2 E 轴为玻璃通窗面密度按玻璃幕墙计算取 1.8 kN/m2 纵向框架梁自重标准值 : 0.35×0.75×25=6.56 kN/m 次梁自重标准值: 0.35×0.75×
25=6.56 kN/m
图 3.4集中荷载传递图
a. A 轴纵向框架梁传来恒荷载标准值 集 标 A G (1).一、二层:
窗的重度:0.45KN/m2
A 轴墙体自重 3.6×(7.5-0.4) ×2.2-3.6×1.5×1.8×(2.2-0.45)=40.01kN 纵向框架梁自重 6.56×(4.8+2.4)=47.23KN 次梁自重 6.56×8.75×0.5=28.54 kN 楼面恒荷载传来荷载
()[]KN
10. 8313. 5234. 28. 4212/7. 84. 22/7. 84. 221
=??
????????++-??橫墙自重:3.6×8.7×2.2/4=17.23KN
KN 11. 216G A =集 标
A 轴上柱的自重 0.4×0.4×3.6×25=14.4 kN
KN 34. 2344. 1411. 216G A =+=总
(2).三层:
窗的重度:0.45KN/m2
A 轴墙体自重 4.2×(4.6+2.4) ×2.2-3.6×1.5×1.8×(2.2-0.45)=46.68kN 纵向框架梁自重 6.56×(4.8+2.4)=47.23KN 次梁自重 6.56×8.75×0.5=28.54 kN 楼面恒荷载传来荷载
()[]KN
10. 8313. 5234. 28. 4212/7. 84. 22/7. 84. 221
=??
????????++-??橫墙自重:4.2×8.7×2.2/4=20.10KN
KN 65. 225
G A ='集 标 A 轴上柱的自重 0.4×0.4×4.2×25=16.8 kN
KN 91. 2468. 1665. 225
G A =+='总
b. B 轴纵向框架梁传来恒荷载标准值:集 标 B G (1).一、二层:
B 轴墙体自重:3.6×(7.5-0.4) ×2.2=57.02N 纵向框架梁自重标准值:0.35×0.75×25=6.56 kN/m 纵向框架梁自重:6.56×(4.8+2.4)=47.23KN 次梁自重: 6.56×8.7×0.5=28.54 kN 楼面恒荷载传来荷载
()KN 44. 12713. 54. 28. 422/4. 22/17. 84. 22/7. 82. 72. 1=???
?
??????+??+-+?KN
68. 294G B =集 标 B 轴上柱自重: 0.45×0.45×3.6×25=18.23kN
KN 08. 30923. 1868. 294G B =+=总
B 轴墙体偏心附加弯矩:57.92×0.075=4.28KN.m A 轴墙体偏心附加弯矩:40.01×0.075=3KN.m M A 标 =234.34×0.050+3=14.82KN.m M B 标 =294.68×0.025=11.65KN.m
框架梁自重:中间跨 0.35×0.4×25=3.5KN/m 边跨 0.35×0.75×25=6.56KN/m (1).三层:
B 轴墙体自重:4.2×(7.5-0.4) ×2.2=66.52N 橫墙自重:4.2×8.7×2.2/2=40.19
纵向框架梁自重标准值:0.35×0.75×25=6.56 kN/m 纵向框架梁自重:6.56×(4.8+2.4)=47.23KN 次梁自重: 6.56×8.7×0.5=28.54 kN 楼面恒荷载传来荷载
()KN 44. 12713. 54. 28. 422/4. 22/17. 84. 22/7. 82. 72. 1=???
???????+??+-+?KN 49. 308
G B ='集 标
B 轴上柱自重: 0.45×0.45×3.6×25=18.23kN
KN 72. 32623. 1849. 308
G B =+='总 B 轴墙体偏心附加弯矩:66.52×0.075=4.99KN.m A 轴墙体偏心附加弯矩:46.68×0.075=3.5KN.m M A 标 =246.91×0.050+3.5=15.85KN.m M B 标 =326.72×0.025+4.99=13.16KN.m 框架梁自重:中间跨 0.35×0.4×25=3.5KN/m 边 跨 0.35×0.75×
25=6.56KN/m
图 3.5恒荷载图
3.2.2活荷载计算
3.2.2.1屋面活荷载计算 :
屋面为非上人屋面,查得屋面活荷载标准值:0.5 kN/m2
=板 q 0.5×4.8=2.4KN/m
D 4G =A 4G =(2.4×
8.7×0.5+2.4×2.4)×1/2=8.1K B 4G =C 4G =8.1+7.2×1.2×1/2=12.42kN 3.2.2.2楼面活荷载计算
楼面活荷载标准值 :2 kN/m2
=板 q 2×4.8=9.6 kN/m
D G 标 =A G 标 =(2.4×
8.7/2+2.4×2.4) ×2=32.4KN B G 标 =C G 标 =32.4+7.2×1.2×2=49.68KN 3.2.2.3集中荷载偏心产生的弯矩
==D A M M 448.1×
0.05=0.41 KN.m ==B C M M 4412.42×
0.025=0.31KN.m =?==05. 04. 32D A M M 标 标 1.62 KN.m m KN M M C B . 24. 1025. 068. 49=?==标 标
图 3.6活荷载图
3.2.3. 风荷载计算
风压标准值计算公式为 w k =βz μz μs w0
因结构高度 H=18m0.1 此种情况下不起控制作用。所以取 b f ’=2825mm 。 梁内纵向钢筋选用 HRB400(fy =f y’=360N/mm2) ξb =0.518 下部跨间截面按单筋 T 形截面计算,因为: α1f c h f ’ bf ’(ho - hf ’/2)=1.0×14.3×140×2825×(715-140/2) =3647.9KN.M>255.69KNM 属于一类 T 形截面
26
2
620' 16. 999515
9938. 03601069. 2559938
. 0221, 518. 00125. 0210124. 0715
28253. 140. 11069. 255m m f M A h b f M h
s
y s s
s
b s f c s =???==
=-+=
As min =525mm2)
将下部跨间截面的钢筋全部伸入支座。则支座截面可按已知受压钢筋的双筋截面计算 受拉钢筋,因本工程梁端弯矩较小,简化计算,仍可按单筋矩形截面设计。
A 支座截面:
2
6
02
6
20' 160. 225715
989. 03601043. 57989
. 0221, 518. 00227. 0210224. 0715
3503. 140. 11043. 57m m h f M
A h b f M s y s s
s b s f c s =???===-+=
As min=525 mm2)满足要求。 B 支座截面:
2
6
02
6
20' 13. 632715
9682. 036010575. 1579682
. 0221, 518. 00636. 0210616. 0715
3503. 140. 110575. 157m m h f M
A h b f M s y s s
s b s f c s =???===-+=
= As min=525mm2)满足要求。 其他层的配筋计算结果见下表
表 3.8配筋计算结果见下表
3.5.1.2梁斜截面受剪受弯承载力计算:
箍筋采用 HPB235级钢筋, 2/210m N f yv =
AB 跨:V=127.323KN 由
464. 1350
140715=????=β,满足要求。 3.5.2.3框架柱正截面承载力计算
以底层的 B 柱为例。由 B 柱内力组合表,考虑到柱端弯矩较小,支座中心处的弯 矩与支座边缘的弯矩偏差不大,且按支座中心算是偏于安全的,故采用对称配筋。 B 轴柱:
kN bh f N b c b 33. 1383518. 04154503. 140. 101=????==εα (b ξ=0.518) 选最不利组合:
柱顶 :① ???==KN N KNm M 2129.718 93.241, ② ???==KN N KNm M 1796.588 88.232, ③ ???==KN N KNm M 2293.309 52.059
柱底:① ???==KN N KNm M 2151.594 79.694 ,② ???==KN N KNm M 1818.464 80.484, ③ ???==KN N KNm M 2317.920 27.381
以第一种不利组合为例计算: 柱顶:b N ﹤ N 为小偏心受压,
680. 010
718. 21294503. 145. 03
21=???=?=
N A
fc s αζ 1533. 10450
4650
/0<==
h l ,取 ζ2=1.0 mm N M e 781. 4310718. 21291024. 933
6
0=??==
mm e a 20=(﹥
mm h 1530
450
30==) mm e e e a i 718. 6320718. 430=+=+=
1.3230. 1680. 033. 10410718
. 63140011) (14001
1221200
=????+=??
+
=ζζηh l h e i
mm h e e s i 711. 274352
450718. 63 1.3232=-+?=-+
=αη 721. 0)
)((43. 001'
012
10
1=++----=
b c s b c c b bh f h bh f Ne bh f N ξααξβααξξ对称配筋: (8. 01=β)
2
'
0' 01' 536.7) 5. 01(mm h f bh f Ne A A s
y c s s =---=
=αξξα 柱底:b N ﹤ N 为小偏心受压,
0.67310 2151.5944503. 145. 03
21=???=?=
N A
fc s αζ 1533. 10/0<=h l ,取 ζ2=1.0
mm N M e 37.04010
2151.59410 79.6943
6
0=??== mm e a 20=(﹥
mm h 1530
450
30==) mm e e e a i 040. 5720040. 370=+=+=
1.3580. 1673. 033. 10410040
. 57140011) (14001
1221200
=????+=??
+
=ζζηh l h e i mm h e e s i 267.460352
450
040. 57358. 12=-+?=-+
=αη 0.732)
)((43. 00
1' 012
10
1=++----=
b c s b c c b bh f h bh f Ne bh f N ξααξβααξξ (8. 01=β)
2
'
0' 01' 447.3) 5. 01(mm h f bh f Ne A A s
y c s s =---=
=αξξα A s min=0.002bh=0.002×450×450=405mm2 其他各柱正截面受弯承载力计算如下表:
表 3.11柱正截面受弯承载力计算表
3.5.2.4垂直于弯矩作用平面的受压承载力验算 按轴心受压构件验算:KN N 82. 2283max =
91. 955
. 045. 50==b l 查表的:981. 0=? =+=) (9. 0' ' s y c u A f A f N ?0.9×0.981×(14.3×550×550+360×12×153.9) =4406.2KN﹥ max N 满足要求。
3.5.2.5斜截面受弯承载力计算
以 B 轴柱为例 一层最不利组合 ??
?
??===KN V KN N KNm
M 63. 286. 171698. 88
剪跨比 80. 451
. 0290. 420=?==
h h n λ﹥ 3 (取 3=λ) 25503. 143. 03. 0??=A f c =1297.7KN﹤ N 取 N=1297.7KN
510
210107. 129707. 051055043. 175
. 11063. 2807. 075. 13
300???-???-?=--
=h f N bh f V s
A yv t sv
﹤ 0
按构造配筋。取井字形复式箍 8@200φ 其余各柱斜截面受剪承载力计算 如下表
作文十:《土木工程专业毕业设计案例》6400字
土木工程专业毕业(结构)设计案例
以下仅为工程概况,方便工程对比,更有完整论文、图纸、计算书共享。 工程一
本建筑位于贵州省凯里市,场地地形平坦。建筑正北方与正西方为主要交通道路,建筑正南方(背面)为住宅楼。由主管批准拟建基地平面图见附图。本建筑为凯里市第一中学教学楼,占地面积1005.58m 2。建筑为地上5层,其建筑平面形式为“一”字形框架结构,室内外高差0.60m ,建筑总高度22.80m ,总建筑面积5027.90m 2。建筑为横向、竖向双向对称结构。
本工程结构形式为五层钢筋混凝土框架结构,建筑物总高度为22.80m ,抗震设防烈度为7度,设计基本地震加速度为0.10g, 设计地震分组为第一组,框架结构抗震等级为二级,结构安全等级为二级,结构的使用年限为50年。室内设计标高为±0.000,相对于绝对标高529.00m, 室内外高差为600mm 。建筑物的耐火等级为二级。
工程二
建筑地点:云南省曲靖市麒麟区
建筑类型:四层大学生教学楼设计,钢筋混凝土框架结构,工程所在地抗震设防烈度为6度,设计基本地震加速度为0.15g ,设计地震分组为第二组,场地类别为Ⅱ类,结构抗震等级为二级,建筑抗震设防类别为乙类,结构安全等级为二级,使用年限为50年。
建筑面积:4592.72m 2。建筑高度:14.7m 。
主体为一字型四层现浇钢筋混凝土框架结构,建筑物总高14.7m ,抗震设防烈度为7度,设计基本地震加速度为0.15g, 设计地震分组为第二组,建筑抗震设防类别为乙类,框架结构抗震等级为二级,结构安全等级为二级,周期比为0.92,结构正常使用年限为50年。室内设计标高为±0.000,室内外高差为450mm 。 工程三
建筑结构类型采用钢筋混凝土框架结构,上人屋面,建筑抗震设防类别为乙类[10],建筑场地Ⅱ类,抗震设防烈度为6度,此为教学楼,设计时提高1度设防,设计基本地震加速度0.05g [15],抗震设防烈度取7度[10],抗震等级为三级[15];地震分组为第二组,地面粗糙度类别为B 类;结构安全等级为二级[9],耐火等级为二级[5],设计使用年限为50年。当地全年主导东北风,基本风压0.30 KN/m2(R=50),基本雪压0.10 KN/m2(R=50),基本温度-1~34℃[14]。
本教学楼主体为四层框架结构,建筑总高度为15.15m ,抗震设防烈度为7度,设计基本地震加速度为0.10g [10], 设计地震分组为第二组[15],建筑抗震设防类别为乙类[10],框架结构抗震等级为三级[15],结构安全等级为二级[9],结构正常使用年限为50年。室内设计标高为±0.000,相对于绝对标高0.450m, 室内外高差为450mm 。建筑物的耐火等级为二级[5]。图纸中尺寸以mm 计,标高以m 计。 工程四
建筑结构类型采用钢筋混凝土框架结构,屋面设计为上人屋面,建筑抗震设防类别为乙类[10],建筑场地Ⅱ类,该地区抗震设防烈度为6度,设计基本地震加速度0.05g [15],此为教学楼,设计时提高1度设防[10],地震分组为第一组,抗震等级为三级[15];当地全年主导东北风,基本风压0.30 KN/m2(R=50),基本温度1~30℃[14],地面粗糙度类别为B 类;结构安全等级为二级[9],耐火等级为二级[5],设计使用年限为50年[16]。
本教学楼主体为4层框架结构,建筑物总高度为15.15m ,抗震设防烈度为7度,设计基本地震加速度为0.10g [10],设计地震分组为第一组[15],建筑抗震设防类别为乙类[10],框架结构抗震等级为三级[15],结构安全等级为二级[9],结构正常使用年限为50年[16]。室内设计标高为±0.000,相对于室外地坪标高0.450m ,室内外高差为450mm 。建筑物的耐火等级为二级[5]。图纸中标高以m 计,尺寸以mm 计。由于建筑物总长度为79.75m ,超过了《混凝土结构设计规范》(GB50010-2010)第9.1.1条伸缩缝最大间距为55m 要求,因此在建筑中部设置了50mm 的伸缩缝的情况下,在施工时应加强构造措施,以减小温度等因素造成的伸缩影响。
工程五
工程名称:成都市锦江区第一中学教学楼;
建设地点:成都市锦江区;
工程规模:总建筑面积4350平方米,建筑层数5层建筑总高度19.8m ; 结构类型:框架结构,合理使用年限为50年;
建筑防火分类:乙类耐火等级二类;
抗震设防烈度:七度;
屋面防水等级:二级;
计量单位:本设计除了标高以米为单位,其余均以毫米为点位 。
地质资料:土的类型划分为:第1层耕土为软弱土,第2层残积土为中硬土,第3层强风化花岗岩为坚硬土。
场地土的特征周期(卓越周期)为0.45s ,勘测时间,勘测范围内未见地下水。
抗震等级为二级。
基本风压: 0 =0.30kN/m2
雪压:0.25 kN/m2,地面粗糙度类别为B 类。
不上人屋面活荷为0.5kN/m2,走廊活荷载为2.5 kN/m2、楼梯活荷载3.5kN/m2,卫生间楼面活荷载为2.5kN/m2,教室、办公室楼面活荷为2.5 kN/m2。 工程六
本工程名称为:资阳市二中教学楼修建工程。建筑单位是资阳市教育投资发展有限责任公司。建筑地点位于四川省资阳市中心。建筑面积为4335m ㎡。建筑层数为地上四层。建筑耐火等级为二级。工程主体为四层框架结构,建筑物总高17.7m ,抗震设防烈度为7度,设计地震分组为第一组,设计基本地震加速度为0.05g ,框架结构抗震等级为三级,结构正常使用年限为50年。室内设计标高为±0.000,室内外高差为450mm 。建筑物耐火等级为二级。
本工程主体为四层框架结构,建筑物总高20m ,抗震设防烈度为7度,设计地震分组为第一组,设计基本地震加速度为0.05g ,框架结构抗震等级为三级,结构正常使用年限为50年。室内设计标高为±0.000,室内外高差为450mm 。建筑物耐火等级为二级。图纸中尺寸以毫米计,标高以米计。建筑物中设置100mm 沉降缝。
工程七
本项目位于广元市苍溪县,建设占地面积23400平方米,东西长180米,南北宽130米。教学楼建筑面积为5345.21平方米,建筑高度21.7米。拟建场地北临城市绿地,其余三面临路,地势平坦,视野开阔,交通便利。
建筑类型:五层教学楼设计,钢筋混凝土框架结构,工程所在地抗震设防烈度为7度,设计基本地震加速度为0.10g ,设计地震分组为第二组,场地类别为乙类,结构抗震等级为三级,结构安全等级为一级,耐火等级为Ⅱ级。
本工程主体为五层框架结构,建筑物总高度为21.70m ,抗震设防烈度为7度,设计基本地震加速度为0.10g, 设计地震分组为第二组,特征周期0.40s 。 建筑抗震设防类别为乙类,框架结构抗震等级为三级,结构安全等级为一级,结构正常使用年限为50年。室内设计标高为±0.000,相对于绝对标高0.300m, 室内外高差为300mm 。建筑物的耐火等级为二级。
工程八
本办公楼为4层钢筋混凝土框架结构体系,建筑面积约5115.06m 2。教学楼各层建筑平面图、剖面图、里面图、门窗表等如建筑图所示。其中普通教室若干,教师及行政办公室9间,休息室4间,小会议室1间,计算机房3间,体育器材
房一间,英语口音兼控制室一间,门卫室1个卫生间男女各8间,化学、物理实验室及其仪器准备室各1间,音乐教室及乐器室各1间,保健室1间及门厅,基本满足在校师生的需要。
本办公楼1层建筑层高为3.9m ,2-4层的层高都为3.6m ,小塔楼层高为3m 。1层的结构层为3.9m (从基础梁顶面算起),2-4层的结构层层高为3.6m ,小塔楼层高为3m ,室内外高差0.30m ,建筑设计使用年限50年。本工程建筑形式为现浇钢筋混泥土框架结构,抗震设防烈度为7度。建筑结构安全等级为乙级,耐火等级为二级,建筑合理使用年限为50年。本工程标高±0.000相当于绝对标高420.5m (黄海高程系统)。
自然表面0.5m 的地表耕植土,重度γ=17.0kN/m3;耕织图以下为1.5m 厚的粉土,重度γ=18.0kN/m3。粉土以下为稍密卵石层8-10m 。地基承载力特征值f ak =300kPa;基础埋深和基础宽度地基承载力修正系数分别为ηd =3;ηb =4.4;地下水位-5m ,无侵蚀作用。
抗震设防烈度为7度,设计基本地震加速度值为0.1g ,地震分组为第二组,建筑场地类别为Ⅱ 类。但根据《关于学校、医院等人员密集场所建设工程抗震设防要求确定原则的通知》(中震防发[2009]49号),该工程地震动峰值加速度提高至0.20g ,地震力计算按0.20g 计算。建筑场地类别:Ⅱ类,特征周期为0.40S 。本工程按设防烈度为8度采取抗震措施,框架抗震等级为二级,设计地震分组为第二组。地面粗糙度类别为B 类。
全年主导东北风,基本风压:0.30kN/m2,基本雪压:0 kN/m2 。
工程九
本工程位于城区,建筑耐火等级为二级,建筑设计使用年限为3类(50年),抗震设防烈度为七度,场地为二类,建筑抗震等级为三级,耐火等级为二级,建筑合理使用年限为50年。
1 结构形式:框架结构。
2 地质条件:建筑物所在场地地面平坦,从上至下分为地表耕植土厚 0.5m .粉土厚 1.5m,稍密卵石厚 8~10m ,下为基岩,地下水位在地表-5m 以下,地质结构稳定。
3 气象资料:该地区主导风向为东北风,基本风压0.70KN/M,基本雪压0.00KN/M。最高气温37℃,最低气温3℃。
4 设备条件:所有设备均由建筑公司提供。
5 总建筑面积:4008.10平方米;建筑占地面积:867.32平方米。
6 建筑层数:四层。
7 建筑高度:从室外地坪至屋面口的高度为19.2米。
8 建筑地点:福建省福清市城区内
本工程主体为四层框架结构,建筑物总高度为19.20m ,抗震设防烈度为7度,设计基本地震加速度为0.10g, 设计地震分组为第三组,建筑抗震设防类别为丙类,框架结构抗震等级为二级,结构安全等级为二级,结构正常使用年限为50年。室内设计标高为±0.000,相对于绝对标高0.450m, 室内外高差为450mm 。建筑物的耐火等级为二级。
工程十
本工程建筑总面积为4244.85m 2,建筑占地面积为1210.15 m 2,建筑总高度为14.4m 。根据规划要求,建筑层数4层,层高为3.6m 。其中普通教师若干,教室及行政办公室9间,休息室4间,小会议室1间,计算机房3间,体育器材房一间,英语口音兼控制室一间,门卫室1个卫生间男女各8间,化学、物理实验室及其仪器准备室各1间,音乐教室及乐器室各1间,保健室2间及门厅,基本满足在校师生的需要。
本工程建筑形式为现浇钢筋混泥土框架结构,抗震设防烈度为7度。建筑结构安全等级为乙级,耐火等级为二级,建筑合理使用年限为50年。本工程标高±0.000相当于绝对标高420.5m (黄海高程系统)。
本工程位于四川省遂宁市,属于四川盆地中亚热带地区,气候温暖湿润,雨势同季,雨量充沛,但分布不均匀,温度较为平衡,夏无酷暑,冬无严寒且日照时间稍短,干湿两季分明,年平均气温17.2℃,年平均日照总数1134.6h ,年平均降雨量1025,8mm ,全年无霜期330天左右,四季特征是:春季回暖交晚,冷空气活动频繁,气候较为多变;夏季气温高,雨量充足;秋季气温下降快,多阴雨;冬季多阴天,少雨雪,是有发生冬旱,基本风压W 0=0.30kN/m2。
本工程选址在四川省遂宁中学原校区内,地质条件:从上到下分别为地表耕植土厚0.5m ,粉土厚1.5m 稍密卵石厚8-10m ,下为基岩,地下水位在-5m 以下,地质结构稳定。
工程十一
本建筑位于乐山市犍为县县城,地势平坦,交通方便,利于材料的运输,占地面积1318.9m 2,建筑为地上4层框架结构,结构安全等级为二级,室内外高差
0.45m ,首层层高4.2m ,标准层层高3.6m ,上人屋面楼梯井高2.7m ,总高17.7m ,建筑总面积5216.4m 2。
本工程主体为四层钢筋混凝土框架结构,建筑总高17.7m ,抗震设防烈度为7度,设计基本地震加速度为0.10g ,设计地震分组为第二组,框架结构的抗震等级为三级,结构安全等级为二级,结构正常使用年限是50年,室内设计标高为±0.000,室内外高差为0.45m ,建筑物耐火等级为二级,图纸中标高以米为单位,其余尺寸以毫米为单位,建筑物总长度为54m ,满足《混凝土规范》规定的框架结构伸缩缝最大间距为55m 的要求,因此不设置伸缩缝。
工程十二
建筑地点:四川 内江市。
建筑类型:五层教学楼的设计,钢筋混凝土的框架结构,工程所在地的抗震设防烈度要求为6度,但教学楼设计时要加设一度来设防,也就是7度设防。设计基本地震加速度为0.05g ,设计地震分组为第一组,场地类别为Ⅱ类,结构抗震等级为三级,结构安全等级为二级,耐火等级为Ⅱ级。 建筑面积:4188.272㎡左右。
本工程主体为五层框架结构,建筑物总高度为21.60m ,抗震设防烈度为7度,设计基本地震加速度为0.05g, 设计地震分组为第一组,建筑抗震设防类别为乙类,框架结构抗震等级为三级,结构安全等级为二级,结构正常使用年限为50年。室内设计标高为±0.000,相对于绝对标高0.450m, 室内外高差为450mm 。建筑物的耐火等级为二级。
工程十三
建筑地点:福建省莆田市
建筑类型:实验中学教学楼,钢筋混凝土框架结构,主楼为5层,辅楼一为5层,辅楼二为3层,整体建筑外形呈现为凹字型,建筑总面积为4923.19m 2,室内外高差0.45m ,首层层高为3.6m ,其余楼层也均为3.6m 。
结构特点:本工程所在地抗震设防烈度为7度[3] ,设计基本地震加速度为0.10g ,设计地震分组为第三组[3] ,场地类别为Ⅱ类[3] ,结构抗震等级为二级[3] ,结构安全等级为二级[3] ,设计使用年限50耐火等级为Ⅱ级[8] 。 全年主导风向:东北风;夏季主导风向:北风;
常年降雨量为:1500.00mm ;
基本风压为:0.50kN/m2;
基本雪压为:0.00kN/m2。
抗震设防烈度为7度[3] ,设计基本地震加速度为0.10g [3] , 设计地震分组为第三
组[3] ,建筑抗震设防类别为乙类[3] ,由于是公共建筑,将其框架结构抗震等级提高一级[3] ,故其结构抗震等级为二级[3] ,结构安全等级为二级[3] ,结构正常使用年限为50年。建筑物的耐火等级为二级[8] 。
工程十四
工程主体为四层框架结构,建筑层数为地上四层,底层高4.2m ,其他各层为3.6m ,总高18.6m 。抗震设防烈度为6度,设计地震分组为第一组,设计基本地震加速度为0.05g ,框架结构抗震等级为三级,结构正常使用年限为50年。
(1)南方丘陵地区,全年最高气温35℃,最低气温-1.5℃,年平均气温15℃。
(2)全年主导风向:西南风;基本风压:0.20kN/m2。
(3)年降雨量:950mm ;日最大降雨量:100mm 。
(4)最大积雪厚度:20mm ;基本雪压:0.1kN/m2。
(5)土壤最大冻结深度:-1.14m 。
(6)地震烈度:6度,地震分组为一组。
从上到下分为地表耕植土厚0.5m, 粉土厚1.5m, 稍密卵石厚8-10m, 下为基岩,地下水位在地表-5m 以下,地质结构稳定。
本工程主体为四层框架结构,建筑物总高18.6m ,抗震设防烈度为6度,设计地震分组为第一组,设计基本地震加速度为0.05g ,框架结构抗震等级为三级,结构正常使用年限为50年。室内设计标高为±0.000,室内外高差为450mm 。建筑物耐火等级为二级。图纸中尺寸以毫米计,标高以米计。建筑物中设置100mm 沉降缝。
倘若有一个工程适合您
愿意为您提供指导和帮助